PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 61:

    You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

    A. Project scope statement
    B. Project schedule network diagram
    C. Activity list
    D. Organizational process assets

  • Question 62:

    You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?

    A. Analogous estimate
    B. Broad estimate
    C. Rough order of magnitude
    D. Expert judgment

  • Question 63:

    Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the work that is remaining in the project. Alice, one of Gary's project team members, consistently reports that she's late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is causing other delays in the project. What is the review of the late work commonly called?

    A. Variance analysis
    B. Leadership
    C. Quality control
    D. Discipline

  • Question 64:

    Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project's ability to finish by a given deadline?

    A. The project must use internal team members to complete the project work.
    B. The project must adhere to several regulations.
    C. The project must use the BGH company to deliver the software portion of the project.
    D. The project must not exceed $1,250,000.

  • Question 65:

    You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

    A. Identify typical schedule milestones.
    B. Create parametric estimates for repetitive activities.
    C. Save time creating activity duration estimates.
    D. Import activity attributes.

  • Question 66:

    Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

    A. Soft logic describes activities that do not have particular resources assigned to them.
    B. Soft logic describes activities that can be completed in any order.
    C. Soft logic describes activities that can have lead time added to them.
    D. Soft logic describes activities that can be crashed because they are effort-driven.

  • Question 67:

    You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

    A. Communications bull's eye
    B. Performance goals
    C. Earned value management goals
    D. Project exception report

  • Question 68:

    Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

    A. Resource competition
    B. Matrix organization
    C. Resource requirement
    D. Resource constraint

  • Question 69:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

    A. 1.02
    B. 0.98
    C. 0.90
    D. -$108,120

  • Question 70:

    You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

    A. Work performance measurements
    B. Corrective actions
    C. Trim the project scope
    D. Causes of variances

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.