PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 81:

    You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

    A. Stakeholder classification
    B. Project management team's classification
    C. Assessment information
    D. Identification information

  • Question 82:

    Della works as a Project Manager for BlueWell Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?

    A. Project is right on target.
    B. Project is ahead of the schedule.
    C. Project is behind the schedule.
    D. Costs are higher than planned.

  • Question 83:

    Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

    A. $176,675
    B. $122,845
    C. -$85,000
    D. -$51,000

  • Question 84:

    Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

    A. Diane
    B. Project sponsor
    C. Risk owner
    D. Subject matter expert

  • Question 85:

    Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?

    A. Schedule analysis
    B. Resource leveling
    C. What-if scenario analysis
    D. Root cause analysis

  • Question 86:

    Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

    A. Quality inspections and compliance
    B. Location, logistics, and resource availability analysis
    C. Labor productivity studies from previous similar projects in the area
    D. The average price of general labor in the area

  • Question 87:

    Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

    A. 140
    B. 10
    C. 325
    D. 5

  • Question 88:

    Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

    A. Add lead time to the painting activity.
    B. Change the relationship of the carpet activity and the painting activity to finish-to-finish.
    C. Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.
    D. Add lag time to the carpet activity.

  • Question 89:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

    A. -$48,654
    B. 13 percent
    C. -$225,000
    D. 0.98

  • Question 90:

    Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?

    A. Organizational process asset
    B. Lessons learned documentation
    C. Process input
    D. Predecessor project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.