PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 71:

    Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?

    A. Stakeholder assessment information
    B. Stakeholder register
    C. Communications management plan
    D. Stakeholder management strategy

  • Question 72:

    A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?

    A. Problem solving
    B. Team building and human resources
    C. Leading
    D. Communication
    E. Negotiation and influential

  • Question 73:

    You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?

    A. Issue report
    B. Exceptions report
    C. Variance analysis
    D. Performance report

  • Question 74:

    In which of the following process groups does Integration Change Control Process fall?

    A. Execution
    B. Initiating
    C. Planning
    D. Monitoring and Controlling

  • Question 75:

    Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

    A. Stakeholders are usually identified through a stakeholder register.
    B. Stakeholders are identified by the project team, project sponsor, and management.
    C. Stakeholders are identified through the project customers.
    D. Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.

  • Question 76:

    You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

    A. Parametric estimate
    B. Definitive estimate
    C. Analogous estimate
    D. Bottom-up estimate

  • Question 77:

    You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?

    A. +110
    B. -25
    C. -110
    D. +25

  • Question 78:

    You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

    A. Expert judgment
    B. Project charter
    C. Stakeholder analysis
    D. Stakeholder register

  • Question 79:

    Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

    If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

    A. The project will complete on time.
    B. The project will be late by one day.
    C. The project will be late by two days.
    D. The project will be early by two days.

  • Question 80:

    Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority

    and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed.

    What does Anna want to create in this instance?

    A. Power/interest grid
    B. Salience model
    C. Power/influence grid
    D. Communications matrix

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.