PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 11:

    Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

    A. Adding features to the project's product that is not included in the project scope.
    B. Managing the day-to-day events of a project.
    C. Creating software as defined in the project scope.
    D. Completing project activities as start-to-start events.

  • Question 12:

    You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

    A. Project calendar
    B. Resource calendar
    C. Organizational calendar
    D. Company calendar

  • Question 13:

    Andy is the project manager of the NHGQ project for his organization. He has elected to use a three- point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes

    to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects.

    What is a three-point estimate?

    A. Each activity must be estimated for its optimistic, pessimistic, and most likely duration.
    B. Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.
    C. A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.
    D. A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

  • Question 14:

    Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

    A. Project charter
    B. Scope of statement
    C. SOW
    D. WBS

  • Question 15:

    Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?

    A. The schedule performance is better than expected.
    B. The schedule performance is right on target.
    C. The cost performance is better than expected.
    D. The schedule performance is below expectation.

  • Question 16:

    You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

    A. Templates
    B. Rolling wave planning
    C. Decomposition
    D. Expert judgment

  • Question 17:

    Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

    A. $122,845
    B. -$51,000
    C. -$85,000
    D. Zero

  • Question 18:

    You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?

    A. It examines only the non-critical path activities that are considered near critical, if the float is one day or less.
    B. It examines only the critical path activities to determine when the project completion date may be.
    C. It examines the availability of needed project resources to determine when activities may actually happen.
    D. It generates a Gantt chart that reflects the availability of project resources and considers working and non-working days for the project.

  • Question 19:

    Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. Which of the following documents should Don refer to, for the information on the activities and the regulations?

    A. Risk management plan
    B. Activity list
    C. Activity list and attributes
    D. Risk register

  • Question 20:

    John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

    A. Organizational process assets
    B. Cost management plan
    C. Resource calendars
    D. Risk register

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.