PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 51:

    John is the project manager for the ABC project. He is finalizing the budget of the project. He is concerned about the direct costs involved in the project. Which of the following can be considered a direct cost in the project?

    A. Cost of electrical utilities
    B. Salaries of management directly involved in the project
    C. Subcontract cost
    D. Accounting support cost

  • Question 52:

    Fill in the blank with the appropriate word. When activities are logically linked, they become the__________

  • Question 53:

    You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

    A. Project Human Resources Management Plan
    B. Project Staffing Management Plan
    C. Project Communications Management Plan
    D. Project Schedule Management Plan

  • Question 54:

    You are the project manager of the NHG. The following figure represents your project network diagram.

    Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

    A. The critical path will now take 26 days.
    B. The critical path will now take 17 days.
    C. The critical path will now take 23 days.
    D. The critical path will now take 20 days.

  • Question 55:

    You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?

    A. Spending is right on target.
    B. Costs are lower than planned.
    C. The project is behind schedule.
    D. Costs are higher than planned.

  • Question 56:

    You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

    You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

    A. Five days
    B. Four days
    C. Eleven days
    D. Zero

  • Question 57:

    You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

    MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410

    What will be the cost performance index (CPI) of the project at the current point of time?

    A. 0.923
    B. 1.083
    C. 1.261
    D. 0.792

  • Question 58:

    You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

    A. Estimate activity durations
    B. Estimate activity resources
    C. Control schedule
    D. Develop schedule

  • Question 59:

    You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

    A. It will require fewer resources due to the cut in the project scope.
    B. It will require additional resources for the additions to the project scope.
    C. It will require additional resources if it is to finish in the same amount of time, as originally predicted.
    D. It will require a new scope baseline to reflect the management change in the project approach.

  • Question 60:

    You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

    Based on this figure, what is the critical path of this project?

    A. ABEHJ
    B. ACFIJ
    C. ADGJ
    D. ACFGJ

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.