  • Question 311:

    John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

    Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?

    A. Zero
    B. One
    C. Four
    D. Five

  • Question 312:

    You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

    A. Increase the working hours.
    B. Level the project schedule.
    C. Add more workers.
    D. Reduce the project scope.

  • Question 313:

    A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?

    A. As workers complete the installation, efficiency will increase and durations will decrease.
    B. As workers complete the installation, errors and risks will increase the actual completion.
    C. As workers complete the installation, effort will diminish and efficiency will decrease.
    D. As workers complete the installation, labor will diminish so duration will increase.

  • Question 314:

    Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure:

    Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?

    A. Day 20
    B. Day 22
    C. Day 17
    D. Day 19

  • Question 315:

    You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

    A. Risk management plan
    B. Schedule management plan
    C. Risk register
    D. Activity attributes

  • Question 316:

    John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

    What is the cost performance index (CPI) of the project at the current point of time?

    A. 0.96
    B. 1.082
    C. 0.833
    D. 1.0625

  • Question 317:

    Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

    A. Functional manager
    B. Operations manager
    C. Project manager
    D. Seller

  • Question 318:

    You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?

    A. Amount of buffer remaining to the amount of resources available
    B. Amount of buffer remaining to the amount of buffer used
    C. Availability of project resources and project buffer
    D. Amount of buffer needed to the amount of buffer remaining

  • Question 319:

    What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?

    A. ($450,000 - $180,000) / ($450,000 - $191,000)
    B. $450,000 - $477,500
    C. $180,000 / $247,500
    D. $180,000 - $247,500

  • Question 320:

    What is the term assigned to graphic in the figure given below?

    A. Communications bull's eye
    B. Performance goals
    C. Earned value management goals
    D. Project exception report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.