PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 41:

    Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

    A. Risk owner
    B. Harry
    C. Project sponsor
    D. Subject matter expert

  • Question 42:

    Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

    A. Perform resource leveling for the project.
    B. Crash the project schedule.
    C. Fast track the project.
    D. Remove things from the project scope.

  • Question 43:

    You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?

    A. Cabinet procurement December 1, plus 45 days lead time
    B. Cabinet procurement November 15
    C. Cabinet procurement December 1, minus 45 days lead time
    D. Cabinet procurement December 15 minus 45 days lead time

  • Question 44:

    You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?

    A. Scope management plan
    B. Performance management plan
    C. Communications management plan
    D. Project management plan

  • Question 45:

    John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

    A. Work performance information
    B. Change requests
    C. Work performance measurements
    D. Forecasting method

  • Question 46:

    Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

    A. Project document updates
    B. Scope baseline
    C. Cost performance baseline
    D. Project funding requirements

  • Question 47:

    You are the project manager of the NHQ project. Your project has a budget of $1,258456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Based on the current performance value what should you report to management regarding the variance at completion?

    A. -$21,618
    B. -$62,922
    C. Zero - you would not know what this will cost until the project is complete.
    D. -$54,044

  • Question 48:

    Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

    A. Reports
    B. Meetings
    C. Diaries
    D. Future planning

  • Question 49:

    Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process? Each correct answer represents a part of the solution. Choose all that apply.

    A. Internal and External
    B. Vertical and Horizontal
    C. Confronting and problem solving
    D. Formal and Informal

  • Question 50:

    Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

    A. Precedence Diagramming Method
    B. Schedule network template
    C. Dependency determination
    D. Activity on the Node

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.