PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 271:

    There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

    A. Scope baseline
    B. Activity attributes
    C. Activity list
    D. Activity resource requirements

  • Question 272:

    All of the following statements about the critical path are false except for which one?

    A. The critical path cannot be crashed.
    B. The critical path is the shortest path in the project network diagram.
    C. The critical path is always one path with the longest duration.
    D. The critical path shows the project's earliest date for completion.

  • Question 273:

    You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to be late on reaching its milestones. What tool and technique can you use as a part of controlling the schedule to help you review various scenarios to bring the schedule into alignment with the plan?

    A. What-if scenario analysis
    B. Root cause analysis
    C. Schedule analysis
    D. Resource leveling

  • Question 274:

    You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

    A. Ideas to action
    B. Problem definition
    C. Problem solution generation
    D. Solution action planning

  • Question 275:

    Fill in the blank with an appropriate phrase.

    The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

  • Question 276:

    You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

    A. Project scope statement
    B. Milestone list
    C. Project schedule network diagrams
    D. Activity list

  • Question 277:

    You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

    A. 32 days
    B. 29 days
    C. 27 days
    D. 26 days

  • Question 278:

    Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk- adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

    A. Crashing
    B. Fast tracking
    C. Critical chain methodology
    D. Adding lead time

  • Question 279:

    You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of the following information except for which one?

    A. Scope baseline
    B. Executing
    C. Scheduling
    D. Estimates

  • Question 280:

    You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

    A. Direct expense
    B. External requirement
    C. Temporary resource
    D. Expert judgment

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.