PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 301:

    You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

    A. Project change control process
    B. Perform integrated change control process
    C. Configuration management
    D. Communications management

  • Question 302:

    Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?

    A. Critical Chain method
    B. Resource utilization
    C. Critical Path method
    D. Resource leveling heuristics

  • Question 303:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

    A. $2,025,000
    B. There is not enough information to know
    C. $4,500,000
    D. $2,250,000

  • Question 304:

    Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?

    A. Code of accounts
    B. Chart of accounts
    C. Component numbering
    D. Activity linkage sequencing

  • Question 305:

    Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?

    A. It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.
    B. They likely do not understand the SPI formula.
    C. It is not good news, as the number should be closer to 100 than 0.
    D. It is good news, but Mark may have large cost variances to achieve this value.

  • Question 306:

    Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below:

    MeasurementsValues BCWP (or EV) 425 BCWS (or PV) 400 ACWP (or AC) 510 What is the schedule performance index (SPI) of the project at the current point of time?

    A. 1.082
    B. 0.88
    C. 1.0625
    D. 0.96

  • Question 307:

    Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?

    A. Current status of risk and issues
    B. Quality control activities
    C. Analysis of past performance
    D. Work to be completed next

  • Question 308:

    Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?

    A. Constructability Analysis process
    B. Schedule Maintenance process
    C. Schedule Development process
    D. Perform Integrated Change Control process

  • Question 309:

    You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

    A. It means the largest schedule variance you can have is five percent.
    B. It is the earned value divided by the planned value for your project.
    C. It is the expectation of management to be 95 on schedule at 95 percent of the project.
    D. It means you will need to earn at least 95 cents per dollar invested in the project.

  • Question 310:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up posed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule variance?

    A. 10 percent
    B. -$48,654
    C. -$225,000
    D. 0.98

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.