PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 281:

    You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?

    A. Risk activities
    B. Schedule activities
    C. Activity attributes
    D. Schedule milestones

  • Question 282:

    Fill in the blank with an appropriate phrase. The _______contains the schedule components and the rules for relating and using the components to represent the process for completing a project.

  • Question 283:

    Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?

    A. $1,312,504
    B. $787,504
    C. $1,812,498
    D. $725,000

  • Question 284:

    Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

    A. Contract
    B. Reserve analysis
    C. Scope baseline
    D. Project schedule

  • Question 285:

    Mark is the project manager of the NHQ Project. Mark wants to create a salience model as part of his communications planning and scheduling. What does a salience model do for a project?

    A. Describes classes of stakeholders based on their power, urgency, and legitimacy.
    B. Classifies stakeholders based on their influence and impact.
    C. Describes classes of stakeholders based on their power and influence.
    D. Groups stakeholders based on their power and interest.

  • Question 286:

    You are the project manager for your organization. Your current project has a schedule variance of - $37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

    A. Your project is likely to be late and over budget.
    B. Your project is performing well.
    C. Your project has a planned value of $600,000.
    D. Your project is six percent off schedule and has a considerable schedule variance.

  • Question 287:

    Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?

    A. Feasibility study
    B. Project charter
    C. Work breakdown structure
    D. Project scope

  • Question 288:

    Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

    A. Functional Management
    B. Project sponsor
    C. Whomever the communications management plan directs her to
    D. Project customer

  • Question 289:

    You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

    A. Contract Types
    B. Expert Judgment
    C. Procurement Negotiations
    D. Make-or-Buy Analysis

  • Question 290:

    You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus on creating time estimates for the most imminent research work and broad estimates for the project work that is coming later in the project. What type of planning are you using in this project?

    A. Milestone planning
    B. Rolling wave planning
    C. Phase gates
    D. Decomposition

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.