PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 291:

    You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

    A. Work breakdown structure
    B. Activity attributes
    C. Resource calendars
    D. Activity list

  • Question 292:

    You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

    A. How the project is performing on its schedule.
    B. Performance of the selected project vendors
    C. Which activities have been started and which activities have been finished.
    D. Percent of completion for the in-progress activities

  • Question 293:

    Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?

    A. .07
    B. 1.07
    C. $34,000
    D. .89

  • Question 294:

    Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

    A. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.
    B. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.
    C. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.
    D. It is a term used to describe activities that are core project management processes, but not core project activities.

  • Question 295:

    You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

    A. To understand the exact type of work the project team will be completing
    B. To help the activity go faster
    C. To get better and more accurate results through the decomposition
    D. To create assignments for the project team as the activities are discussed

  • Question 296:

    Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

    A. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.
    B. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.
    C. The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.
    D. The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

  • Question 297:

    Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?

    A. Imminent activity management
    B. Predecessor-only diagramming
    C. Rolling wave planning
    D. Decomposition

  • Question 298:

    Amy works as a project manager for BlueWell Inc. Her organization wants her to create a new warehouse. Which of the following documents will she create to define the business needs, the project justification, and the current requirements?

    A. Project scope
    B. Feasibility study
    C. Project charter
    D. Work breakdown structure

  • Question 299:

    Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

    A. 48
    B. 55
    C. 54
    D. 40

  • Question 300:

    You are the project manager of the NHQ project. This project is currently running about 15 percent behind schedule and the management has asked you to rectify the problem. You have elected to crash the project. What does this term mean?

    A. Reject all proposed change requests for the project.
    B. Add resources to the project work.
    C. Add cost to the project budget.
    D. Cut non-value added activities to the project.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.