A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?
A. Suggest the product owner start by focusing on the next 2 sprints instead of 10During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach. What should the scrum master do?
A. Discourage the team member from deviating from the plan and document the request during the retrospectiveA product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?
A. Engage the team to determine the sprint velocity based on previous agile projectsWhich of the following is an example of a visual aid used in Lean-Agile software development?
A. Business value delivered chartA new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time. What type of behavior does this describe?
A. SynchronousOsmotic communication is when team members obtain information from overhead conversations.
A. TrueWhich of the following occurs in the first Sprint?
A. Create a project planIdentify the three components of the Agile Triangle. (Choose three.)
A. QualityA project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?" How should the agile lead respond?
A. Total time and average process timeDuring the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them. What should have been done to avoid this?
A. A comprehensive user story with all non-functional requirements should have been createdNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.