  • Question 351:

    Which of the following BEST describes the relationship between portfolios, projects, and programs?

    A. A group of programs makes up a project, and all of an organization's projects make up a portfolio.
    B. A group of projects makes up a program, and all of an organization's programs make up a portfolio.
    C. A group of portfolios makes up a program, and all of an organization's programs make up a project.
    D. A group of projects makes up a portfolio, and all of an organization's portfolios make up a program.

  • Question 352:

    A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?

    A. Network diagram
    B. Ishikawa diagram
    C. WBS
    D. Gantt chart

  • Question 353:

    A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

    A. Add durations.
    B. Add the start and finish dates
    C. Add tasks.
    D. Add resources.

  • Question 354:

    An active project has a CPI of 0.92. Which of the following can be determined?

    A. The project is currently over budget.
    B. The project has a budget surplus.
    C. The project is ahead of schedule.
    D. The project is behind schedule.

  • Question 355:

    Which of the following methods should a project manager use to improve email communication for a time-sensitive, high-visibility global project? (Choose two.)

    A. Limit email recipients to only required team members.
    B. Increase the number of emails to encourage team interaction.
    C. Set up emails with bold text and all caps in the subject line.
    D. Eliminate acronyms from the email to avoid miscommunication.
    E. Include more information to increase the length of each email message.
    F. Include detailed technical consideration in each email.

  • Question 356:

    A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?

    A. Draft a CandD letter and send it to vendor.
    B. Review the MOU with the vendor.
    C. Ask the legal departments to draft a non-complete agreement for the vendor to sign.
    D. Meet with the finance department to prevent the vendor from sending invoices.

  • Question 357:

    A project manager has developed the initial schedule for an upcoming project.

    Using the attached schedule, which of the following is the critical path?

    A. 12 days
    B. 14 days
    C. 16 days
    D. 17 days

  • Question 358:

    A milestone task on the critical path has been completed. Which of the following should the project manager notify?

    A. Owner of predecessor task
    B. Project team
    C. Project sponsor
    D. Project steering committee

  • Question 359:

    The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the project manager should take?

    A. Update the documentation.
    B. Implement the change.
    C. Close the project.
    D. Evaluate the impact.

  • Question 360:

    A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST

    appropriate scheduling action?

    A. Analyze the critical path and update the WBS with the new feature
    B. Add the new feature and reprioritize the product backlog
    C. Add the new feature to the next sprint and move the old feature to the following sprint
    D. Conduct a retrospective with the team to discuss the change and introduce the feature

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.