  • Question 361:

    A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.

    Which of the following documents should the project coordinator use?

    A. Risk register
    B. Issue log
    C. Communication plan
    D. Status report

  • Question 362:

    A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?

    A. Project management office
    B. Portfolio
    C. Program
    D. Mission statement

  • Question 363:

    A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

    A. project management plan
    B. scope statements and issue log
    C. project dashboard and status report
    D. action items and meeting minutes

  • Question 364:

    Which of the following inherently affects quality standards?

    A. SLA
    B. MOA
    C. MOU
    D. WBS

  • Question 365:

    A project portfolio will MOST likely align to:

    A. consumer demand.
    B. corporate strategy.
    C. lessons learned.
    D. PMO guidelines.

  • Question 366:

    A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?

    A. Assess the risk register's new items.
    B. Review the task start and finish dates.
    C. Obtain additional resources.
    D. Analyze the assigned hours.

  • Question 367:

    Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.

    Which of the following management styles is the project manager MOST likely using?

    A. Exploitive
    B. Retrospective
    C. Participative
    D. Authoritative

  • Question 368:

    A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?

    A. Determine the critical path.
    B. Determine the milestones.
    C. Set phase gates
    D. Set a baseline.

  • Question 369:

    Which of the following describes a project's budget overrun?

    A. The project spends only half of the funds.
    B. The project spends only the allocated funds.
    C. The project spends none of the funds.
    D. The project spends in excess of the funds.

  • Question 370:

    A project manager for a projectized organization is notified that a team member is ill and will be out for an extend period of time. This team member is the only person with a key skill set.

    Which of the following should the project manager notify FIRST regarding the team member's absence?

    A. Project sponsor
    B. Human resources office
    C. Budget office
    D. Project team

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.