  • Question 721:

    A customer has requested additional features for an active project. Which of the following steps should take place NEXT?

    A. Implement the requested changes.
    B. Evaluate the impact of the changes.
    C. Update all project documents.
    D. Submit the requested changes to the CCB.

  • Question 722:

    A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?

    A. Project schedule
    B. Issue log
    C. Risk register
    D. Scope statement

  • Question 723:

    A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor. Which of the following terms describe this requirement?

    A. Outsourcing
    B. Business acquisition
    C. Business process change
    D. Internal reorganization

  • Question 724:

    A politically sensitive project is being proposed. The sponsor decides to outsource the work despite having a highly capable team. Which of the following BEST describes the risk mitigation strategy being used?

    A. Acceptance
    B. Avoidance
    C. Transference
    D. Exploitation

  • Question 725:

    A company has decided to bring in outside consultants to assist with the risks that have the greatest effects. The consultants will take ownership of those risks and will be contractually liable if the impact is greater than a predetermined cost value. Given the information in the table below:

    Which of the following risks have the GREATEST effect?

    A. 1, 2, 3
    B. 1, 2, 5
    C. 1, 3, 5
    D. 2, 4, 6
    E. 4, 5, 6

  • Question 726:

    During an active project, the finished deliverables become subject to new regulatory standards, and a new testing process must be included. Which of the following constraints is influencing this project?

    A. Scope creep
    B. Resources
    C. Quality
    D. Requirements

  • Question 727:

    A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?

    A. SLA
    B. SOW
    C. LOI
    D. RFQ

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.