  • Question 341:

    A project manager is sending regular status reports; however, many team members seem to be unaware of the overall project status. Which of the following should the project manager do NEXT?

    A. Begin sending the status updates via text.
    B. Call each team member and provide an update.
    C. Review the status report distribution list.
    D. Schedule a meeting to review the status.

  • Question 342:

    A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

    A. Individually call all project team members.
    B. Send an email to all project team members.
    C. Schedule a conference call.
    D. Schedule a face-to-face meeting.

  • Question 343:

    Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop. Which of the following steps should the project manager take NEXT?

    A. Supply Ann with the requested tablet.
    B. Have Ann submit a change request.
    C. Provide Ann with a copy of the project management plan.
    D. Inform Ann that she will receive what has been authorized.

  • Question 344:

    In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?

    A. The project is behind schedule
    B. The project is over budget
    C. The project has float available
    D. The project needs a gate review

  • Question 345:

    A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?

    A. Risk register
    B. Post-mortem analysis
    C. Issue log
    D. Procurement report

  • Question 346:

    While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources based upon priorities, and optimizing resource deployment between projects. Which of the following BEST describes these actions?

    A. Portfolio management
    B. Agile management
    C. Project management
    D. Strategic management

  • Question 347:

    Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

    A. SOW
    B. PO
    C. SLA
    D. MOU

  • Question 348:

    A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:

    1.

    Project description

    2.

    Draft project timeline and schedule

    3.

    Rough milestones

    4.

    Draft project budget

    5.

    Draft resources required

    6.

    High-level risk review

    Which of the following sections should be included in this document?

    A. Business information
    B. Full risk assessment results
    C. Draft work breakdown structure
    D. Full resource requirements

  • Question 349:

    Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.

    Which of the following MOST likely explains this issue?

    A. Risks were not identified.
    B. Risks were not mitigated.
    C. Risks were not exploited.
    D. Risks were not communicated.

  • Question 350:

    A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

    A. Project schedule
    B. Project management plan
    C. Project charter
    D. Staffing matrix

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.