  • Question 1:

    A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)

    A. Milestones

    B. Stakeholder changes

    C. Audits

    D. Schedule changes

    E. Incident response

    F. Business continuity response

    G. Risk register updates

  • Question 2:

    The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?

    A. Network diagram

    B. Product backlog

    C. Program

    D. Portfolio

  • Question 3:

    A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?

    A. Update the issue log.

    B. Update the risk register.

    C. Conduct a risk review meeting.

    D. Submit a change request to address the risk.

  • Question 4:

    Which of the following indicators would help the project manager to determine the financial status of the project?

    A. CV

    B. SV

    C. EV

    D. PV

    E. COQ

    F. AC

    G. BAC

  • Question 5:

    In a weak matrix, a highly skilled project team member has been using company equipment to view inappropriate content. Which of the following steps should the project manager take FIRST to address this issue?

    A. Send an email outlining the company's acceptable use policy to the employee.

    B. Arrange a face-to-face meeting with the team member.

    C. Contact the team member's manager to address the problem.

    D. Restrict the team member's equipment access.

  • Question 6:

    There is friction between team members who were on the team before a merger took place and those who transitioned during the merger. This situation is having an adverse effect on team performance. Which of the following can the project manager do to help resolve this issue?

    A. Observe the team during the transition period and give the team time to form.

    B. Engage in relationship building by getting both sides to work on tasks together.

    C. Report the conflict to human resources and let them address it.

    D. Assign tasks between the team members to ensure interaction is limited.

  • Question 7:

    Which of the following is primarily responsible for developing the timeline?

    A. Project sponsor

    B. Project coordinator

    C. Project manager

    D. Project scheduler

  • Question 8:

    A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up to the meeting. Which of the following MOST likely describes why this occurring?

    A. There is no rapport between the team members and the project manager.

    B. The time zone in the one country is outside of working hours.

    C. The meeting is occurring too frequently.

    D. Language barriers prevent team members from participating.

  • Question 9:

    Which of the following will MOST likely result in changes to the project plan?

    A. Departure of the project manager

    B. Departure of the sponsor

    C. Milestone realization

    D. Incident occurrence

  • Question 10:

    A project team learns that potential remodeling on the production floor might occur during the execution

    phase of their project. The project team starts debating the different options available to keep delivering

    without adjusting the schedule.

    Which of the following risk activities is being performed?

    A. Mitigation

    B. Quantification

    C. Planning

    D. Identification

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.