You are a project manager for a company that uses Project Server 2013 in Project Server Permission Mode. You have been managing a project for several months. You go on vacation, and you delegate your project management responsibility to one of your coworkers. Your coworker accepts multiple status updates on the project. When you return, you notice that no project updates are visible in Project Web App (PWA), and there are no status updates awaiting approval. You need to ensure that the previously accepted status updates are visible in PWA. What should you do?
A. Set the date range in the Approval's page to include last week's updates.Your organization uses Project Server 2013. You are the project manager of a schedule. Team Members send you emails with their percentage complete on their assignments. Your organization only uses the following two percentages for
tracking tasks:
50% for tasks that are started
100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks. You need to update the tasks in PWA. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)
A. In PWA, open the Tasks screen, select the task(s), and enter 50% or 100% in the % Complete field.You are a project manager for an organization that uses Project Server 2013. You and other project managers use Project Professional 2013 to manage projects. The resources on your project are overallocated due to work assigned across
the enterprise. As a result, some work on your project does not finish as scheduled. Some tasks are left partially complete. Other tasks did not start at all. You need to resolve this issue.
What should you do?
A. Select all tasks that are partially complete or did not start as scheduled and move incomplete parts to status date.You are a project manager in an organization that uses Project Server 2013. You manage a project that has Baseline0 set. There are enterprise custom fields with formulas that make calculations by using the Baseline0 fields. You are planning a major rescheduling in your project and intend to update the project baseline so the formulas in the enterprise custom fields take the new values of the baseline fields. However, for future reference, you want to keep your original baseline. You need to update the project baseline without losing the original values. What should you do?
A. Open you project in Project Professional 2013. In the Gantt chart view, include all the Baseline0 and Baseline1 fields. Copy and paste all values from Baseline0 to Baseline1. Set a new Baseline0, and save and publish the project.You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled. Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to ensure that resources have the ability to report work actuals per day. What should you do?
A. Set the tracking method to actual work done and work remaining.You are a portfolio manager for an organization that uses Project Server 2013. You plan to create weekly status project reports for your executive team. You want to publish your report only once in Project Web App (PWA). Users must be able to fully interact with the report by adding or excluding fields and by changing the rows or columns fields. You need to create a report that meets these requirements. What should you do?
A. Create a tabular report in Microsoft SQL Server Reporting Services (SSRS).You are a team member in an organization that uses Project Server 2013. Each week you report progress on multiple projects that are managed as Microsoft SharePoint task lists. You need to update task progress on multiple projects from one page. Which page should you use?
A. Tasks page in Project Web App (PWA)You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but no access to Project Professional 2013 for making changes to your schedule. In your organization, projects begin work after the project sponsor provides funding for the first phase of the project. You need to take a snapshot of your schedule and make that information available to the Project Management Office (PMO), who will view it in PWA. What should you do?
A. Set all tasks to auto scheduled and publish the project.You are a project manager in an organization that uses Project Server 2013. You manage two projects named Proj1 and Proj2. You create a deliverable dependency between both projects by taking the following actions:
You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1. The Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
On Proj2, you associate a dependency that has a milestone named Milestone2 to the Deliverable1.
After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1 ahead by five days. You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Open Proj1 in Project Professional 2013, open the dependency panel by choosing the Manage Dependencies option in the Task tab, and select Accept all server changes. Save and publish the project.You work in an organization that uses Project Online. Project managers have full control over resource assignments. You work in the Project Management Office (PMO) and discover that two of your critical resources are overallocated in the Resource Center for future work. They are critical resources because they have specialized skills that no one else in your organization has, and they are integral to several projects. You need to determine how to correct the overallocation of these resources. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Manage resource plan task assignments.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-344 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.