You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule.You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks. You check out your schedule in Project Web App (PWA) for editing and select the newly- added tasks. What should you do next?
A. Set an interim plan.You are an administrator who uses Project Server 2013 and Project Professional 2013. The leadership of your organization asks you to assign resources to teams so that the resources are aligned with a team definition. You need to implement this request. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Go to the Resource Center on Project Server 2013, edit all resources, and assign them to the correct team.The IT department uses Project Online to analyze the projects they will execute the next year. Four projects with their respective priority and costs are shown in the exhibit. (Click the Exhibit button.)

The team needs to get the most value from their portfolio, but some last minute restrictions could change their selection. A mutually inclusive dependency is added between the two CRM projects. A mutually inclusive dependency is also added between the two EPM projects. You need to assist the team in achieving the most value in their portfolio, given the constraints shown in the exhibit. You enforce the dependencies and recalculate the analysis. Which two statements become true? (Each correct answer presents part of the solution. Choose two.)
A. The Portfolio Strategic Value will be of 56%.Your organization is using Project Online to facilitate the selection of optimal portfolios. The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool. You need to ensure the tool provides the expected outcome. Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Create a custom workflow that allows the capture of projects with business-relevant information.You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013. For planning purposes, you need to reserve proposed demand for the final 12 months. What should you do?
A. Create new tasks in the project to represent the unplanned portion of the project. Assign resources to these tasks and set their booking type to committed.You are a project manager in an organization that uses Project Server 2013. Project team members submit updates to tasks through Project Web App (PWA). A project team member clicks Remove Task, and you approve it. You apply this change to the project. The team member indicates that they only want to hide the task from that particular view, not remove the task permanently. You need to ensure the task is returned to the Tasks page so it can be properly hidden. What should you do?
A. Mark the task as active and publish the project.You are a project administrator and are implementing Project Server 2013 for a large organization. You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure. You need employ the correct functionality in order to configure Project Server 2013. What should you do?
A. Define your information hierarchy in the server settings by using the Resource Breakdown Structure (RBS), located in the Enterprise custom fields, and RBS's lookup field table.You are a project manager for an organization that uses Project Server 2013. Only administrators have Project Professional 2013. You use Project Web App (PWA) for schedule management. You modify your schedule after some changes are approved through your organization's Project Scope Change process. You need to set a baseline for the project. What should you do?
A. Ask the administrator to access the project schedule in PWA, select the tasks affected by the change request, and baseline those tasks.A company deploys Project Server 2013 to perform a Portfolio Analysis, which they will use to select the projects they will execute in the next fiscal period. The company establishes the criteria to evaluate the portfolio components, and all business cases must be evaluated under these parameters. When configuring Project Server 2013, the Project Management Office (PMO) finds that the established criteria contain both qualitative and quantitative elements, such as corporate reputation and internal rate of return (IRR). You need to provide a system calculated approach to rank your strategic initiatives against each other. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Create a Business Driver library that captures the criteria in quantifiable impact statements that are specific and measurable.You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool. After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change. You need to solve this problem. What should you do?
A. Change the project priority level of your project to 1000 so that it becomes the highest priority and will be automatically leveled.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-344 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.