You are a project manager for an organization that uses Project Server 2013. Synchronization is enabled. Project Sites at your organization are created by a default template when a new schedule is published. You are the Project Owner of a schedule. You have a Project Site associated with this schedule. You need to quickly change the look and colors of your schedule's Project Site. What should you do?
A. In the Project Site, select the Edit Page option from the ribbon and modify the Project Site.You are a project manager in an organization that uses Project Server 2013. All project managers have permission to edit all projects. You edit a project in Project Web App (PWA), make changes, publish the project, and close your browser. A project manager calls you to report they are unable to open your project for edit in PWA. You need to resolve this issue. What should you do?
A. Advise the project manager to open the project in Project Professional 2013.You work for an organization that uses Project Server 2013. Single-entry mode is disabled. Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following
scenario:
During week one, a team member enters a total of 20 hours of actual work. During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
A. Percent of work completeYou are a program manager for an organization that uses Project Server 2013. You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it. You open the master project and realize that these changes are not reflected in the master project schedule. You need to ensure these changes are reflected in the master project. What should you do?
A. Open the master project in Project Web App (PWA), click on the Calculate Project to calculate all changes, and then publish.You are a project manager for an organization that uses Project Online. You create a resource plan to provide high level resource demand during the portfolio intake and selection process. Your project is now selected for detailed planning. You complete a detailed work breakdown structure (WBS). You need to remove the resource demand from the resource plan What should you do?
A. Change the Calculate From setting on the resource plan.You are a portfolio manager in an organization that uses Project Server 2013. You plan to review the milestones status of a project named Proj1. You need to create a graphical view of all milestones of Proj1 that allows you to see the Start
and Finish dates of each milestone. You need to accomplish this goal in the least amount of time.
What should you do?
A. Open Microsoft Visio and make a data connection against the Project Server database. Write a query that returns the Name, Start, and Finish dates of all milestones of Proj1. Create a chart with that information.You are a project manager for an organization that uses Project Server 2013. One enterprise project has grown in complexity and size; the project manager creates sub- sites to organize the work by team. All the teams are comfortable working with a familiar tool, such as the Microsoft SharePoint site. However, management cannot view all of the work being performed in the portfolio, and they need to permanently make decisions about the best use of the resources. You need to bring all of this work into visibility in the least amount of time and without affecting current resource processes. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
A. Add the SharePoint Sites to Project Web App from the Project Center.You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time
correcting the data problems. You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
Review the project data after the project managers create the projects. Send the projects back to the project managers if you find incorrect data so that they can make the appropriate corrections.
Repeat the data verification process unless the data does not have any errors. Publish a project only when all of its data is correctly completed.
What should you do?
A. Instruct the project managers to include a task named project review every time they create a project and assign it to you. Project Server will notify you about the project creation. If you find an error, delete the project, and the project manager should create the project again.You are a resource manager and manage a project with Project Server 2013 and Project Professional 2013. Without notice, one of your key resources decides to take a leave of absence for 30 days. You need to account for the absent resource and assess how the absence will affect your schedule. What should you do?
A. Open Project Professional 2013 and manually reschedule the tasks associated with constraint dates which start when the resource returns.DRAG DROP
You are a project manager for an organization that uses Project Server 2013. You check out a project for editing in Project Professional 2013 and discover that one resource is overallocated across three projects. You need to determine the cause of the overallocation by using the Team Planner view to resolve the issue. Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-344 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.