In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
A. Ask the team to focus only on the goal, not on ad hoc meetings.A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving conflicting resource requirements from the team, sponsor, and key stakeholders.
What should the project manager do next?
A. Identify the resources that are agreed upon to initiate the project and request additional resources later.A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.
What should the project manager have done to prevent this?
A. Developed a detailed, phased procurement management plan including all activities required and had the client approve it.A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service.
What should the project manager do next?
A. Evaluate the impact of this decision and communicate with management.A project manager notices that a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories.
What should the project manager do first?
A. Increase the sprint duration to accommodate the additional work.A new employee has joined the management team and wants to get a quick overview of all the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?
A. Review the information radiators for each project.A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested. What should the project manager do next?
A. Reject the changes and stay the original course as initially agreed with the client.A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A. Reject the changes as the lead time is too short.A project team used agile approaches to create a minimum viable product (MVP). Currently, the team is discussing the possible next steps. What should be the next step?
A. Break down the user stories into the smallest size possible.During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?
A. Wait for the next project status meeting to evaluate the impact of one less resource.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.