DRAG DROP
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved.
Drag the scenario on the left to the correct risk response strategy on the right.
Select and Place:

As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?
A. Ensure that the whole team is appropriately recognized and organize a project farewell party to celebrate the project success and closure.Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests. What should the project manager do next?
A. Refer to the requirements traceability matrix.A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry. How should the project manager communicate the organizational culture and project goal to these stakeholders?
A. Hire a company to advertise the project and company through a media outlet.During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A. Check with the team to learn what can be done, and consult an expertA project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.
In which stage of the project would the project manager need a greater effort to lead them?
A. PerformingThe project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A. Conveyed task completion information to accountingA project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated by other team members. Which three actions should the project manager take? (Choose three)
A. Allow team members to resolve personal issues without involving the project managerA customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?
A. Test product integration in accordance with the requirements.A project manager is executing a project where an external vendor will provide some deliverables. After awarding the contract to the vendor, the project manager is informed that the vendor is running behind schedule on a separate project. Finding another vendor will exceed the budget.
What should the project manager update first?
A. Issue logNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.