PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 101:

    Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

    A. -$75,500
    B. -$390,000
    C. -$487,500
    D. -$65,000

  • Question 102:

    The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

    A. Activity list
    B. Milestone list
    C. Activity attributes
    D. Project document updates

  • Question 103:

    You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

    A. Direct expense
    B. External requirement
    C. Temporary resource
    D. Expert judgment

  • Question 104:

    You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

    What is the critical path of this project?

    A. ABEHJ
    B. ACFGJ
    C. ADGJ
    D. ACFIJ

  • Question 105:

    Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

    A. Lesson learned documentation
    B. Risk analysis
    C. Preventive action
    D. Corrective action

  • Question 106:

    Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

    A. Cost variances and Cost Performance Index
    B. Scope baseline
    C. Performance measurement baseline
    D. Schedule variances, planned value, and the Schedule Performance Index

  • Question 107:

    You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?

    A. Organizational process asset
    B. Scheduling tool
    C. Project Management Information System
    D. Project office software

  • Question 108:

    Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

    A. People will behave based on what their behavior brings them.
    B. As employees do repetitive tasks, duration should decrease.
    C. Work expands to fill the amount of time allotted to it.
    D. An exponential increase labor does not correlate to an exponential decrease in duration.

  • Question 109:

    You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to- complete performance index based on the current BAC?

    A. 1.02
    B. 0.010
    C. 0.75
    D. 0.95

  • Question 110:

    Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.