PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 221:

    Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

    A. Project charter
    B. Project scope statement
    C. Project communications management plan
    D. Resource calendar

  • Question 222:

    Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

    A. -$75,000
    B. -$42,000
    C. -$45,000
    D. -$65,000

  • Question 223:

    You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

    A. You are creating an analogous estimate.
    B. You are creating a bottom-up estimate.
    C. You are relying on expert judgment.
    D. You are creating a rough order of magnitude estimate.

  • Question 224:

    You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

    Based on this diagram, find out the earliest day on which Activity G can be started.

    A. Day 13
    B. Day 7
    C. Day 22
    D. Day 17

  • Question 225:

    You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

    A. Wednesday
    B. Thursday
    C. Monday
    D. Tuesday

  • Question 226:

    Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

  • Question 227:

    You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?

    A. Work expands to fulfill the amount of time allotted to it.
    B. Risks will be allowed into activities in which management creates risk provisions.
    C. Laborers will create errors when time has been allotted for errors to exist.
    D. Errors will be allowed into assignments when management creates error opportunity.

  • Question 228:

    Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

    A. -$98,217.78
    B. -$44,198
    C. $441,025.64
    D. $243,219.78

  • Question 229:

    Which of the following provides a method to track project progress during project execution against what was planned?

    A. Team members profile
    B. Benefit-cost ratio
    C. Schedule baseline
    D. Detailed project budget

  • Question 230:

    Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

    A. Scope of statement
    B. Project charter
    C. Statement of work (SOW)
    D. WBS

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.