PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 231:

    Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

    A. Mandatory dependencies
    B. Required dependencies
    C. Discretionary dependencies
    D. External dependencies

  • Question 232:

    You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

    A. A significant point in the project
    B. A goal of reaching a significant delivery of project benefits by an identified date
    C. An imposed date for the project to reach a given point
    D. The completion of a project activity that is crucial to project completion

  • Question 233:

    Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

    A. Scope Verification
    B. Configuration Management System
    C. Project Management Information System
    D. Integrated Change Control

  • Question 234:

    The figure given below demonstrates the communications model for a project. What role does component C play in the communication model?

    A. Encoder
    B. Transporter
    C. Sender
    D. Medium

  • Question 235:

    You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

    A. -$75,000
    B. $350,000
    C. .82
    D. -$187,500

  • Question 236:

    Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?

    A. Hard logic describes activities that can be completed in any order but are positioned with finish-to- start relationships.
    B. Hard logic describes activities that have external constraints, such as a vendor.
    C. Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.
    D. Hard logic describes activities that must be completed in a particular order.

  • Question 237:

    Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?

    A. Idea/mind mapping
    B. Nominal group technique
    C. Delphi technique
    D. Affinity diagram

  • Question 238:

    Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

    A. Procurement document
    B. Contract
    C. Business case
    D. Project statement of work

  • Question 239:

    You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that you will need to report to management?

    A. -$62,922.80
    B. $1,312,504
    C. $1,525,000
    D. $787,504

  • Question 240:

    You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

    A. Critical path scheduling
    B. Time-oriented scheduling
    C. Resource-oriented scheduling
    D. Network scheduling

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.