PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 171:

    Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

    A. Conflict resolution should focus on issues, not personalities.
    B. Conflict is natural and forces a search for alternatives.
    C. Openness resolves conflict.
    D. Conflict is an individual issue.

  • Question 172:

    Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

    A. Critical chain method
    B. Risk analysis method
    C. Activity on the arrow method
    D. Critical path method

  • Question 173:

    You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

    A. $142,000
    B. $232,000
    C. $41,750
    D. $23,750

  • Question 174:

    The figure given below demonstrates the communication model for a project. What role does the component D play in the communication model?

    A. Sender
    B. Medium
    C. Encoder
    D. Transporter

  • Question 175:

    What is the formula to find the schedule performance index?

    A. EV-PV
    B. EV/AC
    C. EV/PV
    D. EV-AC

  • Question 176:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are upposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. Based on the estimate at completion, what is this project's to-complete performance index?

    A. -$108,120
    B. 1.02
    C. $4,608,120
    D. 0.98

  • Question 177:

    Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

    A. Expert judgment
    B. Analogous estimate
    C. Templates
    D. Parametric estimate

  • Question 178:

    Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?

    A. - $210,000
    B. - $720,000
    C. - $250,000
    D. - $270,000

  • Question 179:

    Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should Jack tell the management?

    A. $1,087,497.74
    B. $755,000.56
    C. $1,112,978.45
    D. $790,988.76

  • Question 180:

    Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

    A. Identify stakeholders
    B. Performance reporting
    C. Plan communications
    D. Stakeholder analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.