PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 161:

    Examine the figure given below.

    In this project network diagram, what is the total float for Activity I?

    A. Three
    B. Zero
    C. Five
    D. One

  • Question 162:

    Examine the figure given below:

    You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailability of the resources from the vendor. What will this delay do to your project completion, if you allow the delay to enter into the project?

    A. The project will be one day late.
    B. The float for activity D will be consumed.
    C. The project can still finish on time.
    D. The project will be seven days late.

  • Question 163:

    Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

    A. Risk response
    B. Team development
    C. Risk mitigation
    D. Corrective action

  • Question 164:

    You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?

    A. Activity attributes
    B. Project management plan
    C. Schedule Management Plan
    D. Roles and Responsibilities Matrix

  • Question 165:

    You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

    A. Project communications management plan
    B. Project reporting structure
    C. Project schedule
    D. Project scope management plan

  • Question 166:

    You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

    How much float can you use on Activity G if Activity B actually takes eight days to complete?

    A. Four
    B. Three
    C. Seven
    D. Zero

  • Question 167:

    You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

    A. -$135,000
    B. .67
    C. .81
    D. -$65,000

  • Question 168:

    You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

    A. $306,000
    B. .94
    C. $344,250
    D. .75

  • Question 169:

    You work as a project manager for BlueWell Inc. You are going through a project with your project team. Some of your project team members are reporting that their activities are running late because there are lag times between activities that do not need to be there. You examine the schedule and see that the lag times have been incorporated into the project schedule for quality control reviews. You also learn that the quality control reviews are not being completed as planned. What is the best approach in this scenario?

    A. Since the quality control inspections are not being completed, remove the lag time from the project.
    B. Take corrective action and determine when the quality control inspection has happened so far in the project, perform quality control on the deliverables where the inspection was skipped, and ensure that quality control will happen from this point forward.
    C. Since the quality control inspections are not being completed, take corrective action and ensure that the inspections continue from this point forward.
    D. Discuss with the project team that the lag times should not affect the project schedule because they were built into the project schedule to begin with. Even if the quality control inspections were happening the time was allotted in the schedule for the inspections.

  • Question 170:

    You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

    A. 48
    B. 20o, 45m, 90p
    C. 90
    D. 45

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.