PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 191:

    You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path. What are schedule activities on the critical path called?

    A. Critical activities
    B. Action items
    C. High alert activities
    D. Red rated activities

  • Question 192:

    You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?

    A. Nothing, the 45 hours limit is a guideline.
    B. The project will take longer to complete.
    C. The project will take less time to complete.
    D. The project will require more resources.

  • Question 193:

    Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

    Based on the network diagram, find out which path is the critical path for this project?

    A. ABEHJ
    B. ABDIJ
    C. ABDHJ
    D. ACFIJ

  • Question 194:

    You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

    A. Decomposition
    B. Rolling wave plan
    C. Precedence diagramming method
    D. Templates

  • Question 195:

    Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

    A. Scope baseline
    B. Organizational process assets
    C. WBS
    D. Enterprise environmental factors

  • Question 196:

    You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier

    and a scope of work description for each activity in the activity list.

    Why is this information needed?

    A. To track the work to the project requirements
    B. To maintain profit and loss statements for the project
    C. To help the project team understand what work is required to be completed
    D. To communicate the work to be completed to the project stakeholders

  • Question 197:

    You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?

    A. Expert judgment
    B. Enterprise environmental factor
    C. Resource limitation
    D. Organizational process asset

  • Question 198:

    You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

    A. Resource calendars
    B. Schedule data
    C. Activity list
    D. Project scope statement

  • Question 199:

    Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

    A. 0.98
    B. -$16,677
    C. 1.07
    D. 0.94

  • Question 200:

    Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?

    A. Activity Name
    B. Activity ID
    C. Risk event
    D. WBS ID

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.