PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 111:

    Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?

    A. Stakeholder identification tools
    B. Expert judgment
    C. Stakeholder Analysis Matrix
    D. Communications management plan

  • Question 112:

    You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

    A. The duration will increase, but the labor will stay the same.
    B. The duration will decrease as new team members are brought onto the project.
    C. Nothing, new resources will be incorporated into the project team.
    D. The duration will increase, but the labor will decrease.

  • Question 113:

    Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?

    A. The activities must be of fixed duration.
    B. The activities must be effort-drive.
    C. The activities must not be susceptible to the Law of Diminishing Returns.
    D. The activities must be risk-free.

  • Question 114:

    Which of the following statements best describes an activity in a project?

    A. It is a defined set of functions a resource must complete for the project scope to be considered complete.
    B. It is the effort needed to complete a work package.
    C. It is the unit of resource utilization needed to complete a project deliverable.
    D. It is a listing of all project work that must be accomplished for the project scope to be considered complete.

  • Question 115:

    In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

    A. Estimate activity resources
    B. Define activities
    C. Control schedule
    D. Develop schedule

  • Question 116:

    Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

    A. Archive the project records.
    B. Summarize the project risks costs.
    C. Summarize the project variance.
    D. Close the project office.

  • Question 117:

    Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

    A. 1.23
    B. 100 percent because the vendor caused her lateness
    C. .80
    D. $524,000

  • Question 118:

    Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

    A. Work performance measurement
    B. Stakeholder expectation management
    C. Project communication management
    D. Stakeholder analysis

  • Question 119:

    Which of the following is NOT an output of the control schedule process?

    A. Organizational process assets
    B. Change requests
    C. Project termination request
    D. Project document updates

  • Question 120:

    You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

    A. Assumption
    B. Risk
    C. Resource requirement
    D. Resource constraint

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.