PMI-SP Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Jun 09, 2026

PMI PMI-SP Online Questions & Answers

  • Question 121:

    What project management plan will document the time frame and frequency for the distribution of required information?

    A. Scope Management Plan
    B. Communications Management Plan
    C. Stakeholder Management Plan
    D. Schedule Management Plan

  • Question 122:

    You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

    A. Schedule data
    B. Work performance information
    C. Project management plan
    D. Project schedule

  • Question 123:

    Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

    A. $163,626
    B. $130,901
    C. -$985,040
    D. 0.16

  • Question 124:

    You are the project manager for your company. You are working with the activities defined in the figure below.

    What will happen to your project if Activity F takes five additional days to complete than what was expected?

    A. Your project's critical path will shift to ACFI.
    B. Your project will be late by five days.
    C. Your project can still complete on time as float is available on Activity I.
    D. Your project will now have two critical paths.

  • Question 125:

    What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

    A. Scope Verification
    B. Configuration Management System
    C. Project Management Information System
    D. Integrated Change Control

  • Question 126:

    John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.

    A. Concrete
    B. Pre-construction
    C. Engineering
    D. Conceptual engineering

  • Question 127:

    You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

    A. Fast tracking only works if activities can be overlapped to shorten duration.
    B. Fast tracking only works if the activities are effort-driven.
    C. Fast tracking only works if the activities are resource-driven.
    D. Fast tracking only works if activities can have start-to-start relationships.

  • Question 128:

    You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

    What will be the cost variance (CV) of the project at the current point of time?

    A. +80
    B. -80
    C. -10
    D. +10

  • Question 129:

    You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?

    A. 11,667
    B. $-111,750
    C. There is no variance.
    D. $7,000

  • Question 130:

    John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

    A. Hammocks
    B. Critical path scheduling
    C. Flags
    D. Tasks

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.