PMI PMI-ACP Online Questions & Answers

  • Question 541:

    Which management style does Agile advocate?

    A. Task
    B. Team
    C. Product
    D. Performance

  • Question 542:

    A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the scrum master and asked for a bi-weekly status report because they feel they are not being properly updated. How should the scrum master respond to this request?

    A. Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.
    B. Create and update bi-weekly project status reports for the stakeholder who requested the report.
    C. Escalate this to the stakeholder's supervisor because this is an unreasonable request.
    D. Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

  • Question 543:

    A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

    A. Escalate the concern to the project sponsor for necessary action
    B. Adjust the feature to make it work as needed
    C. Work directly with the customer to arrive at a suitable compromise
    D. Log this into the risk register and inform the team at the next standup meeting

  • Question 544:

    Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint goals. What should the scrum master do next?

    A. Alert the team that sprint goals might not be met and create an alternative plan
    B. Obtain team buy-in to perform modifications to the sprint backlog
    C. Have the sprint proceed as planned
    D. Ask the team to decide if the task should be reassigned

  • Question 545:

    The development team should have a lead developer to ensure the work is properly executed.

    A. True
    B. False

  • Question 546:

    The Scrum Team and Development Team are the same thing.

    A. True
    B. False

  • Question 547:

    A client states that a product is not being built as requested. How should the agile team address this?

    A. Conduct an internal review to validate functionality before shipping
    B. Audit the quality control process to ensure that the product adheres to requirements
    C. Lengthen iterations to ensure there is sufficient time to build functionality
    D. Hold product review sessions with the client to obtain product acceptance

  • Question 548:

    On what should Agile estimates be based?

    A. A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan
    B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes
    C. Ball park figures collected from past Agile projects with scopes similar to the current project
    D. Initial resource breakdown based on the available person days in the full project duration

  • Question 549:

    A project team's standups often run over the allotted time as members attempt to resolve issues. With a large team, this is leading to productivity impacts and bringing complaints from some members that the meetings are wasting their time when they are not directly involved in an issue's resolution. How can the project leader help to manage the team's time?

    A. Set up individual status meetings and find ways to make sure issues are resolved in advance so that time is not wasted for all team members during the standups.
    B. Add time to the standups to accommodate issue-resolution discussions so that everyone is up to date on the decisions made.
    C. Change the standups to weekly status meetings with a longer duration to allow team members to resolve issues collaboratively.
    D. Ask team members to raise issues during standups and then discuss resolution options with specific members in separate conversations.

  • Question 550:

    Which of the following is NOT one of the 12 core practices of XP?

    A. Visualize the flow
    B. On-site Customer
    C. Coding Standards
    D. System Metaphor

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.