  • Question 331:

    A PM is reviewing objectives for a project in a new industry. Which of the following items should the PM review first?

    A. Applicable regulations and standards
    B. Relevance to the global environment
    C. Company vision, mission, and values
    D. Impact to the corporate brand

  • Question 332:

    During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

    Average worked hours

    Which of the following describes the result?

    A. A negative correlation exists between the number of mistakes and the working hours.
    B. No correlation exists between the number of mistakes and the working hours.
    C. A low correlation exists between the working hours and the number of mistakes.
    D. A positive correlation exists between the number of mistakes and the working hours.

  • Question 333:

    An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

    A. Rollback plans
    B. Project management plan
    C. Deployment plan
    D. Asset management plan
    E. Communication plan
    F. Resource management plan

  • Question 334:

    A software development team implemented an approved change but does not obtain the expected results.

    The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?

    A. Scope creep
    B. Recovery plan
    C. Incident report
    D. Risk response

  • Question 335:

    A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

    A. Use an on-premises project management scheduling tool.
    B. Limit access to members of the project team.
    C. Mandate overtime to get the project completed sooner.
    D. Ensure all team members have signed a non-disclosure agreement.

  • Question 336:

    During the kickoff meeting, a stakeholder raises a concern that an assigned responsibility is outside of the stakeholder's domain.

    Which of the following would MOST likely be the reason?

    A. The communication plan is outdated.
    B. The project manager did not assess the stakeholders.
    C. The project manager did not update the risk register.
    D. The statement of work does not reflect the impacted stakeholders.

  • Question 337:

    Which of the to and allowing interactive feedback from a project team?

    A. Text message
    B. Chat
    C. Email
    D. Videoconference

  • Question 338:

    During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

    A. Schedule
    B. Status report
    C. Issue log
    D. Task board

  • Question 339:

    A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical.

    Which of the following should the project manager do first?

    A. Review the project charter.
    B. Start the process of engaging the stakeholders.
    C. Arrange a kickoff meeting.
    D. Evaluate potential risks.

  • Question 340:

    The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

    A. External
    B. Internal
    C. Mandatory
    D. Discretionary

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.