  • Question 601:

    The executive sponsor asks a project manager to summarize the following for a project:

    1.Final capital expenditures.

    2.Anticipated cost of new employee resources to support the solution.

    3.Maintenance estimates.

    Which of the following information should the project manager provide?

    A. Cost baseline
    B. Burn rate
    C. Cost variance report
    D. Total project cost

  • Question 602:

    A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

    A. Signed contracts
    B. Archived documentation
    C. Project closeout report
    D. Lessons learned

  • Question 603:

    A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

    A. Documentation
    B. Team collaboration
    C. Gap analysis
    D. Training sessions
    E. Touch points
    F. Progress monitoring

  • Question 604:

    A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

    A. Review of existing artifacts
    B. Development of an issue log
    C. Identification and assessment of stakeholders
    D. Establishment of accepted communication channels

  • Question 605:

    A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

    A. Submit a change request.
    B. Evaluate the impact of the change.
    C. Get approval from the CCB.
    D. Communicate the change to stakeholders.

  • Question 606:

    A new project manager was assigned to a project during the execution phase.

    The project manager discovers a lot of potential areas that may prevent the project from completing deliverables

    Which of the following should the project manager do first?

    A. Review the project risk register.
    B. Update the defect tracker.
    C. Meet with stakeholders to discuss concerns.
    D. Add the potential blockers to the issues list.

  • Question 607:

    A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

    A. Identify project risks and plans to address them.
    B. Identify business needs and product descriptions.
    C. Create a work breakdown structure for the project.
    D. Create a work schedule for the project team to follow.

  • Question 608:

    Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

    A. Data security
    B. Operational security
    C. Physical security
    D. Digital security

  • Question 609:

    During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

    A. Procurement
    B. Communication
    C. Quality assurance
    D. Risk

  • Question 610:

    A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

    A. Too much time might be spent generating project delays.
    B. The project manager might be seen as weak.
    C. The number of change requests throughout the project might be reduced.
    D. Some stakeholders might not be completely satisfied.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.