CompTIA PK0-005 Online Questions & Answers

  • Question 351:

    A senior leadership team has requested a way to be informed about a project without having to look through emails or hold another meeting.

    Which of the following would best serve the needs of the senior leadership team?

    A. Wiki knowledge base
    B. Project dashboard
    C. Gantt chart
    D. Project status report

  • Question 352:

    A project manager and IT manager are working on developing operational training and hand-off procedures, as well as considering a move-to-production date.

    Which of the following are the project manager and IT manager working on?

    A. Risk plan
    B. Transition plan
    C. Communications plan
    D. QA plan

  • Question 353:

    A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

    A. Key stakeholder identification
    B. Preliminary procurement
    C. Solution design determination
    D. Critical factor enlistment

  • Question 354:

    During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?

    A. Create a change request for the change advisory board.
    B. Work with the business analyst to document the new epic.
    C. Reject the change to prevent scope creep.
    D. Update the risk register and the work in the mitigation plan.

  • Question 355:

    Which of the following describes three-tier architecture?

    A. Conceptual, design, and implementation stages
    B. Presentation, application, and data processing
    C. Network, software, and security
    D. Development, testing, and production environment

  • Question 356:

    A project manager has been assigned a project consisting of team members from multiple time zones. The project manager is trying to establish proper communication channels to use for project communications.

    In which of the following phases is the project manager working?

    A. Initiation
    B. Monitoring and controlling
    C. Planning
    D. Execution

  • Question 357:

    Project stakeholders are concerned that a project might not finish on time due to previous slippage.

    Which of the following is the best way for the project manager to determine how much longer the project will take, assuming the project team will continue to work at the current production rate?

    A. Estimate by using the baseline divided by the schedule performance index for critical path tasks.
    B. Report the budgeted cost of work scheduled and the budgeted cost of work performed.
    C. Ask an external consultant for their projection based on experience and industry standards.
    D. Assess the schedule reserves to determine if it is adequate for the remaining risk.

  • Question 358:

    Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the

    meeting on another day.

    Which of the following techniques is the project manager using?

    A. Avoiding
    B. Smoothing
    C. Forcing
    D. Compromising

  • Question 359:

    A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

    A. Review the detailed plan.
    B. Develop a preliminary scope.
    C. Develop a transition plan.
    D. Develop a project management plan.
    E. Review the resource pool.
    F. Review the project objectives.

  • Question 360:

    Which of the following describes KPIs?

    A. Analyses of organizational strengths and weaknesses
    B. Graphical representations of process flow
    C. Elements against which performance can be measured
    D. Collaboration platform tools

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.