  • Question 321:

    In the kickoff meeting, a project manager announced the project will use a tool to store documents, artifacts, and any other data relevant to the project. The tool will perform version control, maintain retention data, and archive destruction or historical information.

    Which of the following is being described?

    A. Record management system
    B. Project dashboard
    C. Backlog
    D. Wiki knowledge base

  • Question 322:

    Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

    A. Telephone
    B. Videoconference
    C. Face-to-face
    D. Email

  • Question 323:

    During an important stage of a project, a project team is suffering from burnout, which is impacting the quality of the work. The project manager analyzes the feasibility of approving additional time off.

    Which of the following will allow the project manager to reduce the pace of the work to mitigate these concerns?

    A. Contingency reserves
    B. Escalation to the steering committee
    C. Backlog prioritization
    D. Critical path

  • Question 324:

    Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

    A. Rollback plan
    B. Downtime stage
    C. Maintenance window
    D. Validation checks

  • Question 325:

    During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO.

    Which of the following should be the project manager's next step?

    A. Create a transition plan.
    B. Add training to the schedule.
    C. Update the project charter
    D. Involve the CCB.

  • Question 326:

    A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?

    A. Inform all stakeholders.
    B. Update the issue register.
    C. Follow the escalation path.
    D. Initiate a change request.

  • Question 327:

    A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase.

    Which of the following best describes the team life cycle?

    A. The team members are in a conflict that affects their relationship.
    B. The team members perform as a well-organized unit.
    C. The team members have met and are learning about the project.
    D. The team members have completed the work and are moving on from the project.

  • Question 328:

    Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

    A. Social
    B. Regulatory
    C. Environmental
    D. Governmental

  • Question 329:

    Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

    A. The team is working in different rooms within the same building.
    B. The team is working remotely two days per week.
    C. The team has members distributed around the world in different time zones.
    D. The team is based in the same office but has a large number of members.

  • Question 330:

    In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

    A. Add a new risk.
    B. Perform an impact analysis.
    C. Escalate to the sponsor.
    D. Raise a change request.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.