PK0-004 Exam Details

  • Exam Code
    :PK0-004
  • Exam Name
    :CompTIA Project+
  • Certification
    :CompTIA Certifications
  • Vendor
    :CompTIA
  • Total Questions
    :727 Q&As
  • Last Updated
    :Feb 23, 2025

CompTIA PK0-004 Online Questions & Answers

  • Question 71:

    The responsibility of estimating how long a task will take belongs to the:

    A. project scheduler
    B. project team
    C. project manager
    D. project coordinator

  • Question 72:

    A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise. Which of the following contains actions the team is MOST likely to consider?

    A. Identify, collaborate, quantify
    B. Accept, mitigate, transfer
    C. Stop, review, plan
    D. Prioritize, qualify, engage

  • Question 73:

    A project manager is taking over an international project that is in progress and realizes redundant work is being performed by teams in different countries. Which of the following documents would help resolve this issue?

    A. Project scope statement
    B. Project charter
    C. Status report
    D. Project communication plan

  • Question 74:

    A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?

    A. Meeting minutes
    B. Issue log
    C. Project schedule
    D. Budget

  • Question 75:

    A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?

    A. Identifying the risk
    B. Obtaining approval from the CCB
    C. Evaluating the impact of the risk
    D. Communicating to stakeholders

  • Question 76:

    A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

    A. Fast-track the tasks.
    B. Utilize positive float.
    C. Crash the schedule.
    D. Remove the critical path

  • Question 77:

    A project manager is creating the WBS.

    In which of the following phases is the project?

    A. Initiation
    B. Planning
    C. Execution
    D. Closing

  • Question 78:

    An active construction project must make immediate changes when it is discovered that the designated project area contains protected wetlands.

    Which of the following is the MOST likely impact to the project?

    A. The project quality will decrease
    B. The project scope will decrease
    C. The project timeline will increase
    D. The interproject dependencies will increase

  • Question 79:

    Given the information in the table below, which of the following is the total project cost?

    A. $40,000
    B. $70,000
    C. $95,000
    D. $120,000

  • Question 80:

    Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?

    A. The cost will increase.
    B. There will be no impact.
    C. The scope will change.
    D. The schedule will change.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.