  • Question 661:

    Which of the following is the BEST technique for comparing actual or planned project practices to those of comparable projects?

    A. Benchmarking
    B. Pareto chart
    C. Histogram
    D. Fishbone diagram

  • Question 662:

    Which of the following charts is a mathematical diagram used to display values for two variables for a set of data?

    A. Histogram
    B. Fishbone
    C. Gantt
    D. Scatter

  • Question 663:

    A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?

    A. Crashing the schedule
    B. Prioritizing tasks
    C. Determining milestones
    D. Developing sprints

  • Question 664:

    A project manager, who previously worked at a construction firm, has just joined an IT organization and has been assigned to handle a security project. Which of the following roles can provide technical direction during the course of the project?

    A. Security SME
    B. Business analyst
    C. Project scheduler
    D. Project sponsor

  • Question 665:

    Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned.

    Which of the following risk strategies was used?

    A. Accept
    B. Mitigate
    C. Avoid
    D. Transfer

  • Question 666:

    A customer-requested project change has been approved, implemented, and validated. Which of the following should the project manager do NEXT?

    A. Update the project charter.
    B. Update the statement of work.
    C. Update the lessons learned.
    D. Update the project management plan.

  • Question 667:

    Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?

    A. Resources
    B. Requirements
    C. Scope
    D. Funding

  • Question 668:

    A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?

    A. Project schedule
    B. Action items
    C. Project charter
    D. Communication plan

  • Question 669:

    Which of the following describes a burn rate?

    A. The rate at which project documents are disposed.
    B. The rate at which project personnel leave the project.
    C. The rate at which the project budget is used.
    D. The rate at which the timeline increases.

  • Question 670:

    The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?

    A. Projectized
    B. Functional
    C. Matrix
    D. Intermediary

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.