  • Question 681:

    The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

    This type of analysis is an example of which of the following?

    A. Cost performance index
    B. Risk mitigation
    C. Schedule variance
    D. Cost variance

  • Question 682:

    When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

    A. Issue log
    B. Risk management plan
    C. Communications plan
    D. Risk register
    E. Status report

  • Question 683:

    A critical change has been implemented, which the project manager needs to communicate to the project team. Which of the following would be the BEST method for communicating the change?

    A. Fax
    B. Social media
    C. Printed mailing
    D. Email
    E. Text message

  • Question 684:

    Which of the following charts is a graphical representation of the causes of a specific event?

    A. Histogram
    B. Scatter
    C. Fishbone
    D. Gantt

  • Question 685:

    A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

    A. Resource loading
    B. Resource leveling
    C. Prioritizing tasks
    D. Allocating resources

  • Question 686:

    A new project charter is being drafted.

    Which of the following would be the BEST source for the high-level project requirements?

    A. Sponsor
    B. Project manager
    C. Project management office
    D. Project team

  • Question 687:

    Two parties are beginning conversations regarding the purchase of professional services. Which of the following should be in place FIRST?

    A. RFP
    B. SOW
    C. NDA
    D. LOI

  • Question 688:

    The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.

    Which of the following best describes what the PM should work on FIRST?

    A. Project charter
    B. Project schedule
    C. Meeting agenda
    D. Responsibility assignment matrix
    E. Risk register

  • Question 689:

    Two highly skilled resources, who are currently working on other projects, are assigned to a project manager. Personality conflicts between the two resources have adversely affected project completion. The project manager has asked a manager with direct authority over the resources to provide input to resolve the issue, but the project manager does not have the level of authority required to resolve the personality conflict.

    Which of the following structure types is this an example of?

    A. Strong matrix
    B. Balanced matrix
    C. Functional
    D. Weak matrix
    E. Projectized

  • Question 690:

    Which of the following roles would be tasked with project steering?

    A. Project manager
    B. Key project stakeholders
    C. Project management office
    D. Project coordinators

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.