  • Question 621:

    Which of the following should be updated FIRST, once the hurricane season has ended?

    A. Scope statement
    B. Issue log
    C. Risk register
    D. Communications plan

  • Question 622:

    In which of the following situations is a project manager MOST likely to use a process diagram?

    A. When describing a new business idea for the team to review
    B. When describing a new business workflow for the team to implement
    C. When describing a new business project for the team to implement
    D. When describing a new business acquisition for the team to review

  • Question 623:

    Several team members report that meeting objectives are not being met.

    Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)

    A. Create an SOW prior to each meeting and adhere to it.
    B. Create a meeting agenda prior to each meeting and adhere to it.
    C. Create a lessons learned list prior to each meeting and adhere to it.
    D. Create a project charter prior to each meeting and adhere to it.
    E. Create an action item list during the meeting and adhere to it.
    F. Create a corrective action plan prior to each meeting and adhere to it.
    G. Create a WBS prior to each meeting and adhere to it.

  • Question 624:

    Resources for a project report to a project manager and a functional manager.

    The organizational structure is:

    A. Matrix
    B. Ad hoc
    C. Functional
    D. Projectized

  • Question 625:

    A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date. If more resources are provided, which of the following strategies would BEST help to achieve the new date?

    A. Fast track
    B. Burn
    C. Crash
    D. Reduce durations

  • Question 626:

    The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?

    A. Network diagram
    B. Product backlog
    C. Program
    D. Portfolio

  • Question 627:

    An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project. Which of the following is the obstacle?

    A. Ability to identify approval authority
    B. Incomplete change control documentation
    C. Project team autonomy
    D. Change validation process

  • Question 628:

    A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?

    A. Issue log
    B. Status report
    C. Risk register
    D. SOW

  • Question 629:

    Which of the following organizational changes is MOST likely used to transfer staff resources from one city to another to support team activities?

    A. Relocation
    B. Business merger
    C. Outsourcing
    D. Internal reorganization

  • Question 630:

    A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?

    A. Gain approval for the changes.
    B. Identify the approval authority.
    C. Implement the changes.
    D. Create an emergency change request.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.