  • Question 551:

    A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)

    A. Mail the purchase order and follow up with a phone call.
    B. Fax the purchase order and follow up with a phone call.
    C. Drive to the vendor if local and provide a signed purchase order.
    D. Scan and send the purchase order and follow up with a phone call.
    E. Request a courier from the vendor to pick up the purchase order.

  • Question 552:

    During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

    A. Incident response
    B. Project plan
    C. Risk register
    D. Business continuity plan

  • Question 553:

    Which of the following is the primary purpose of an MOA or an MOU?

    A. State expectations of all signatory parties to reduce potential misunderstandings.
    B. Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
    C. Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
    D. Provide transparency to competitors regarding all signatory parties.

  • Question 554:

    An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?

    A. Language barrier
    B. Personal preference
    C. Technological factor
    D. Cultural difference

  • Question 555:

    A functional manager within a project is requesting to edit the display features of an application that is being developed. Which of the following has the authority to approve the edit?

    A. PM
    B. CCB
    C. PMO
    D. SME

  • Question 556:

    A PM is reviewing bids from vendors and has a question.

    Which of the following documents should the PM use to obtain a response?

    A. Project schedule
    B. RFP
    C. Quotation
    D. RFI

  • Question 557:

    Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?

    A. Smoothing
    B. Collaborating
    C. Compromising
    D. Avoiding

  • Question 558:

    A project has activities on the critical path that must be completed before other activities can start.

    Task A is dependent on Task C before Task D can be completed.

    Task A requires task B to start.

    Task B takes twice as long to complete as Task C.

    Which of the following is the appropriate ordering of the critical path?

    A. B, A, D
    B. C, B, D, A
    C. D, A, C
    D. B, C, A, D

  • Question 559:

    A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

    A. Provide the next task to the newly freed resource.
    B. Communicate the success to the team.
    C. Notify the project sponsor of the new completion date.
    D. Update the schedule and add lag to the next task.

  • Question 560:

    A customer-requested change has been denied by the CCB. Which of the following should the project manager do NEXT?

    A. Halt project work until a meeting with the customer and the project sponsor takes place.
    B. Update the project issues log.
    C. Report the denied request to the customer and proceed with project work.
    D. Reestablish the project baselines.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.