  • Question 571:

    Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)

    A. Planned value
    B. Schedule variance
    C. Acceptable variance
    D. Cost variance
    E. Earned value

  • Question 572:

    A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?

    A. In the beginning, projects entail a degree of uncertainty that needs to be specified.
    B. In the beginning, projects have start and finish dates that require elaboration.
    C. In the beginning, projects are part of a program that requires coordination.
    D. In the beginning, projects start with detailed inputs that need to be explained.

  • Question 573:

    Which of the following would indicate a project manager is working in a matrix-based organization?

    A. The project manager has full authority over resources and the project.
    B. The project manager has no authority over the project resources and limited-to-no authority over the project.
    C. Resources align to the project, report to the project manager, and have no functional home at the end of the project.
    D. Resources report to business area functional managers and return to the functional area at the end of the project.

  • Question 574:

    New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.

    Which of the following is the BEST way for the PM to validate the assessment?

    A. Ask the team for estimates, and review the project schedule and budget.
    B. Ask the team to review the product scope and validate its impact on the schedule and quality.
    C. Ask the team for estimates, and review the cost management plan.
    D. Ask the team to perform a SWOT analysis, and validate the assessment.

  • Question 575:

    A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?

    A. The company received a CandD.
    B. A higher-priority project needed the expertise.
    C. The new member did not sign an NDA.
    D. An SLA prevented new team members.

  • Question 576:

    A vendor is late with product deliverables. Which of the following documents should the PM refer to FIRST?

    A. CandD letter
    B. MOU
    C. SLA
    D. SOW

  • Question 577:

    Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

    A. EAC
    B. BAC
    C. TCPI
    D. ETC

  • Question 578:

    Which of the following project management tools provides an authoritative source of the project performance guidelines?

    A. KPI
    B. SWOT
    C. RACI
    D. MOU

  • Question 579:

    A project manager wants to determine the percentage of a project's budgeted costs versus expenditures. Which of the following calculations should the project manager perform?

    A. Burn rate
    B. Critical path analysis
    C. EV
    D. EAC

  • Question 580:

    A project team member has completed an assigned task on time.

    After updating the project schedule, which of the following steps should the project manager take NEXT?

    A. Send an updated schedule to the CCB.
    B. Send a project status update to the sponsor.
    C. Release the team members to the functional manager.
    D. Notify the team members to begin successor tasks.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.