  • Question 41:

    A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)

    A. Business continuity response
    B. Resource changes
    C. Disaster recovery response
    D. Risk response
    E. Gate review

  • Question 42:

    Near the end of a sprint, the IT systems were taken down for a critical patch, and the team was inactive for four hours. The team members are concerned they will not be able to complete their tasks before the end of the sprint. Which of the following BEST describes how the Scrum master should assist the team to finish on time?

    A. Bring the additional resources to help complete the work.
    B. Add the uncompleted work to the product backlog.
    C. Move the work to the next sprint.
    D. Inform the team members they will need to work longer hours.

  • Question 43:

    The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur. Which of the following will assist the project team with building the schedule?

    A. Task sequencing
    B. Task predecessors
    C. Task dependencies
    D. Task prioritizing

  • Question 44:

    Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?

    A. Incident response
    B. Business continuity response
    C. Resource change response
    D. Schedule response

  • Question 45:

    During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training. Which of the following communication methods should be used?

    A. Project communications plan
    B. Project dashboard
    C. Project schedule
    D. Project status report

  • Question 46:

    A project is in the initiation phase. Which of the following tasks will take place during this phase?

    A. Develop a WBS.
    B. Define the project requirements.
    C. Create a project charter.
    D. Acquire the project resources.

  • Question 47:

    Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)

    A. Fishbone diagram
    B. RACI matrix
    C. Monte Carlo
    D. Process flowchart
    E. Expert judgment
    F. Project dashboard

  • Question 48:

    A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.

    Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

    A. Email
    B. Social media
    C. Text messaging
    D. Face-to-face

  • Question 49:

    A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?

    A. Stakeholders
    B. Scrum master
    C. Project sponsor
    D. Project team

  • Question 50:

    A homeowner wants to build a fence. It will take:

    A quarter of a day to measure the length of the fence Half a day to acquire the materials A quarter of a day to dig holes for the posts A quarter of a day to set the posts with concrete Two days for the concrete to dry

    While the concrete is drying, the homeowner will spend a quarter of a day cutting the lateral pieces to size, half a day applying the coating to the remaining pieces, and then three days waiting for the coating to dry. It will then take the homeowner one day to assemble the fence. Which of the following is the length of time it will take the homeowner to build the fence?

    A. Six days
    B. Seven days
    C. Eight days
    D. Nine days

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.