  • Question 321:

    Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below: Which of the following is MOST likely the cause?

    A. Predecessors not properly identified
    B. Scope change
    C. Retrospective in progress
    D. Insufficient resources assigned

  • Question 322:

    The vendor management team has requested all project managers to provide proof to back up complaints on vendor resolution delays. Which of the following will provide this information?

    A. Scope statement
    B. Project plan
    C. Action items
    D. Issue log

  • Question 323:

    The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

    A. Personal preference
    B. Intra-organizational differences
    C. Culture
    D. Time zone

  • Question 324:

    Given the following:

    Which of the following is the duration of the critical path?

    A. 35 days
    B. 37 days
    C. 38 days
    D. 72 days
    E. 73 days

  • Question 325:

    A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?

    A. FF
    B. SS
    C. SF
    D. FS

  • Question 326:

    Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?

    A. Determine the flexibility between the project constraints
    B. Hold a kick-off meeting with the project team
    C. Determine procurement needs to meet the project demands
    D. Create the risk register

  • Question 327:

    A project manager is working on the project charter. Which of the following phases does this describe?

    A. Initiation
    B. Planning
    C. Execution
    D. Closing

  • Question 328:

    A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred?

    A. Risk avoidance
    B. Outsourcing
    C. Business demerger
    D. Business acquisition

  • Question 329:

    Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task

    A. December 18
    B. December 19
    C. December 20
    D. December 21
    E. December 22

  • Question 330:

    The sponsorship of an active project has changed multiple times, and stakeholders have submitted a large number of change requests. Which of the following would be the BEST method to rebaseline the project?

    A. Mandatory meeting
    B. Stand-up meeting
    C. FAQ about the project
    D. Detailed status report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.