  • Question 141:

    To maintain an active project's progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?

    A. Mitigating
    B. Negotiating
    C. Forcing
    D. Avoiding
    E. Accepting

  • Question 142:

    A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

    A. Email
    B. Distribution of printed media
    C. Face-to-face
    D. Video conferencing

  • Question 143:

    A project team is comprised of a mix of in-house and virtual team members. When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

    A. Composing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.
    B. Using text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.
    C. Sending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.
    D. Hosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.

  • Question 144:

    The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?

    A. Instant messaging
    B. Video conference
    C. Phone call
    D. Collaboration website

  • Question 145:

    Which of the following documents need to be updated as events occur during a project? (Choose two.)

    A. Change request
    B. Risk register
    C. Meeting minutes
    D. Issue log
    E. Status report

  • Question 146:

    Which of the following are characteristics of a project? (Choose two.)

    A. A project is a temporary endeavor.
    B. A project provides a unique product, service, or result.
    C. A project is an ongoing endeavor.
    D. A project involves scheduled maintenance.
    E. A project includes life-cycle cost management.

  • Question 147:

    A project manager is managing an eight-month effort and has to report on the financial health once a month. No changes to the project will be approved going forward. Given the following table:

    The project's burn rate is also decreasing by 10% monthly over the remainder of time. Which of the following BEST describes the project's financial health?

    A. The project will burn $36,585, resulting in a net deficit of $11,585
    B. The project will burn $54,615, resulting in a net deficit of $29,615
    C. The project will burn $40,500, resulting in a net deficit of $15,500
    D. The project will burn $45,000, resulting in a net deficit of $20,000

  • Question 148:

    The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager?

    A. Rescheduling
    B. Crashing
    C. Rebaselining
    D. Control scope

  • Question 149:

    A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

    A. durations.
    B. tasks.
    C. critical path.
    D. resources.

  • Question 150:

    Which of the following represents additional unauthorized requirements from the client?

    A. Scope creep
    B. Changing scope baseline
    C. Change request
    D. Gold plating

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.