CompTIA JK0-017 Online Questions & Answers

  • Question 1:

    Which of the following describes a work breakdown structure (WBS)?

    A. Determines the critical path of a project schedule
    B. Identifies stakeholders and their roles
    C. Is deliverable-oriented and hierarchical in nature
    D. Measures the quality of the project objectives

  • Question 2:

    All of the following are considered part of the risk management plan EXCEPT the risk:

    A. register.
    B. matrix.
    C. assessment.
    D. baseline.

  • Question 3:

    Which of the following documents would a project manager review to determine all the identified risks on a project?

    A. Risk matrix
    B. Risk register
    C. Risk response
    D. Risk baseline

  • Question 4:

    Which of the following is included in the project charter?

    A. A work performance report
    B. A cost assessment
    C. A high level plan
    D. A risk assessment

  • Question 5:

    A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?

    A. Schedule optimization
    B. Fast tracking
    C. Resource management
    D. Crashing

  • Question 6:

    The project sponsor has just requested a status report be emailed to all project stakeholders every two weeks. Which of the following documents needs to be updated?

    A. Communications plan
    B. Quality plan
    C. Stakeholder analysis report
    D. Work Breakdown Structure (WBS)

  • Question 7:

    Which of the following is the BEST way for an organization to obtain qualified vendors?

    A. Use the largest vendors with access to enhanced resources.
    B. Use the vendors with the closest location for easy access.
    C. Use the established vendor approval process.
    D. Use the lowest priced vendors.

  • Question 8:

    A customer is reporting that the projects deliverables are not meeting the acceptance criteria. Which of the following documents MOST likely needs to be updated?

    A. Deliverable summary
    B. Quality checklist
    C. Risk register
    D. Resource assignment matrix

  • Question 9:

    A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?

    A. Modify the project schedule.
    B. Obtain approval for the change.
    C. Reduce the amount of project resources to control costs.
    D. Modify the project budget.

  • Question 10:

    In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?

    A. Obtain funding for the project.
    B. Provide quality review of the deliverables.
    C. Provide leadership to the project team.
    D. Obtain resolution of the application development issues.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.