Question 1 Single choice

During which of the following process groups is the availability of required resources for the project determined?

  1. A

    Executing

  2. B

    Monitoring/Controlling

  3. C

    Initiating

  4. D

    Planning

Show answer and explanation

Correct answer: D

Question 2 Single choice

Post-mortem analysis occurs in which of the following process groups?

  1. A

    Closing

  2. B

    Pre-project setup

  3. C

    Monitoring / controlling

  4. D

    Planning

Show answer and explanation

Correct answer: A

Question 3 Single choice

During which of the following process groups is the project charter developed?

  1. A

    Pre-project setup

  2. B

    Project execution

  3. C

    Project planning

  4. D

    Project control

Show answer and explanation

Correct answer: A

Question 4 Single choice

Which of the following is MOST likely to be included in a communication plan?

  1. A

    Change request

  2. B

    Risk register

  3. C

    Frequency

  4. D

    Statement of Work (SOW)

Show answer and explanation

Correct answer: C

Question 5 Multiple choice

Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

  1. A

    Risks

  2. B

    Probability

  3. C

    Cost analysis

  4. D

    Start date

  5. E

    Activity durations

  6. F

    Finish date

Show answer and explanation

Correct answers: D, E, F

Question 6 Single choice

Which of the following is an appropriate risk response for diverting a portion of the project risk?

  1. A

    Avoiding

  2. B

    Sharing

  3. C

    Enhancing

  4. D

    Exploiting

Show answer and explanation

Correct answer: B

Question 7 Single choice

A major change has been approved by the change control board and it now needs to be scheduled for implementation.

Which of the following is the BEST method of implementing the change?

  1. A

    Distribute details of the change per the communication plan, and implement according to the change control process.

  2. B

    Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.

  3. C

    Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.

  4. D

    Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.

Show answer and explanation

Correct answer: A

Question 8 Single choice

Refer to the attached Exhibit.

Which of the following is the float of path Start-C-E-Finish in the network diagram?

  1. A

    Zero

  2. B

    One

  3. C

    Three

  4. D

    Five

Show answer and explanation

Correct answer: A

Question 9 Single choice

Who should conduct lessons learned when an outside vendor is used?

  1. A

    The project coordinator because they are responsible for the project and vendor.

  2. B

    The resource manager because they are responsible for the vendors actions.

  3. C

    The program manger because they control the project budget.

  4. D

    The project manager because they are responsible for the entire project.

Show answer and explanation

Correct answer: D

Question 10 Single choice

Which of the following would require that the project risk register be updated?

  1. A

    A qualitative risk analysis is performed

  2. B

    A stakeholder has concerns about material delays

  3. C

    The risk management plan is created

  4. D

    Increased costs for required materials

Show answer and explanation