  • Question 41:

    Which of the following is true of a work breakdown structure (WBS)? (Select Two).

    A. It consists of work packages at the top level which are decomposed to increasingly detailed levels.
    B. It is a quantitative analysis tool used in quality management to analyze defects.
    C. Each descending level represents an increasing detailed definition of the project work.
    D. It is developed during the planning process and used to create the project scope statement.
    E. It organizes and defines the total scope of the project.

  • Question 42:

    Which of the following would require that the project risk register be updated?

    A. A qualitative risk analysis is performed
    B. A stakeholder has concerns about material delays
    C. The risk management plan is created
    D. Increased costs for required materials

  • Question 43:

    The formal process that must be performed at the end of the project to provide the final inspection of the product is called:

    A. methodology verification.
    B. scope verification.
    C. change verification.
    D. system verification.

  • Question 44:

    A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?

    A. Communications management plan
    B. Cost management plan
    C. Project charter
    D. Contract management plan

  • Question 45:

    During which of the following process groups is the availability of required resources for the project determined?

    A. Executing
    B. Monitoring/Controlling
    C. Initiating
    D. Planning

  • Question 46:

    Which of the following would be goals of an effective kick-off meeting? (Select Two).

    A. To create the project charter
    B. To create the statement of work (SOW)
    C. To outline the communication plan
    D. To set team member expectations
    E. To determine the critical path of the project

  • Question 47:

    Refer to the attached Exhibit.

    Which of the following is the duration of the critical path in the diagram?

    A. 2
    B. 5
    C. 6
    D. 7

  • Question 48:

    A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance?

    A. Acceptance
    B. Transfer
    C. Mitigation
    D. Avoidance

  • Question 49:

    Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?

    A. Risk transfer
    B. Risk avoidance
    C. Risk sharing
    D. Risk mitigation

  • Question 50:

    Which of the following is a component of the cost management plan?

    A. Team member compensation
    B. Statement of Work (SOW)
    C. Project needs assessment
    D. Control limits

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.