  • Question 71:

    Which of the following contract types places the LEAST amount of risk on the seller?

    A. Fixed-Price
    B. Cost-Plus-Fixed-Fee (CPFF)
    C. Cost-Plus-Fee (CPF)
    D. Time and material

  • Question 72:

    A team member reports that a system component they are working on causes the system to continually reboot. The project manager should record this in which of the following documents?

    A. Quality management plan
    B. Communication plan
    C. Risk matrix
    D. Issue log

  • Question 73:

    Two employees will not work on the same project together. The project manager tells the employees to talk to their supervisors because the supervisors recommended they work together. This is an example of which of the following conflict resolution styles?

    A. Withdrawing
    B. Forcing
    C. Accepting
    D. Compromising

  • Question 74:

    When would a project manager have a closure meeting? (Select Three).

    A. Stage completion
    B. Task completion
    C. Document completion
    D. Project cancellation
    E. Project completion
    F. Vendor cancellation

  • Question 75:

    A project manager needs to identify uncertain events during the planning phase. Which of the following documents would be the BEST source of this information?

    A. Quality log
    B. Risk register
    C. Issues log
    D. Responsibility assignment matrix

  • Question 76:

    A project manager is performing activity duration estimation for a project. Using expert judgment the project manager has three values for each activity: the worst case, most likely case, and best case. Which of the following tools would be the BEST to use?

    A. Gantt chart
    B. PERT
    C. EVM
    D. GERT

  • Question 77:

    The project has been terminated. Which of the following should be conducted with the project team before they are released?

    A. Case study
    B. Feasibility analysis
    C. Stakeholder analysis
    D. Post-mortem analysis

  • Question 78:

    A project is cancelled unexpectedly prior to completion. Which of the following would the project manager use to document the details of the project closure?

    A. Histogram
    B. Post mortem
    C. SWOT analysis
    D. Project scope statement

  • Question 79:

    Which of the following would be the BEST tool to estimate activity time durations?

    A. Gantt chart
    B. CPM
    C. Estimating model
    D. PERT

  • Question 80:

    The purpose of a WBS dictionary is to provide:

    A. additional details for each component of the WBS, and for each component provide a brief definition of its statement of work, outputs, actual activities and pertinent milestones.
    B. a detailed glossary of terms used in the WBS.
    C. written authorization to sanction work on a particular work-package within the WBS, and define the methods for its implementation and the monitoring of its performance.
    D. a hierarchical decomposition of the work to be undertaken to address the objectives and meet the requirements of the project at the lowest level.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.