  • Question 71:

    A company has a new Hyper-V host server that runs Windows Server 2012 R2 Datacenter edition. You plan to deploy a new virtual machine (VM). You must install Windows Server 2012 R2 Standard edition on the VM from a standard

    network adapter by using PXE boot. The VM must boot to a SCSI VHDX disk.

    You need to create the VM.

    What should you create?

    A. a storage pool that uses SCSI disks
    B. a Generation 1 VM
    C. a Generation 2 VM
    D. a virtual disk that uses the VHDX format

  • Question 72:

    A company has a single Active Directory Domain Services (AD DS) domain and four Windows Server 2012 R2 servers that have the Hyper-V role installed. The company uses System Center 2012 R2 Virtual Machine Manager (VMM) to manage the Hyper-V environment. One set of Hyper-v host servers is dedicated for use by the development environment. A second set of Hyper-v host servers is dedicated for use by the production environment.

    The network architects assign the IP address subnets as shown in the following table:

    The network architects also prepare a network design for the Hyper-V environments as shown in the Network Design exhibit. (Click the Exhibit button.) The implementation team reports a problem with IP addressing as shown in the Network Error exhibit. (Click the Exhibit button.)

    You need to ensure that the implementation team can implement the network design successfully. For each of the following statements, select Yes if the statement is true. Otherwise, select No. Each correct selection is worth one point.

    Hot Area:

  • Question 73:

    An organization has two teams of developers. One team develops web applications. The other team develops mobile applications. You administer servers for the organization. All four servers run Windows Server 2012 R2 and are part of a

    Hyper-V cluster. You create six virtual machines (VMs) for each team. You plan to create a virtual environment for the teams. You have the following requirements:

    Both teams must use the 10.10.10.0/24 subnet.

    Each VM for the web application team must have network connectivity with all other web application VMs.

    Each VM for the mobile application team must have network connectivity with all other mobile application VMs.

    The VMs for the web application team must NOT connect to the VMs for the mobile application team.

    You need to create the network for the VMs. What should you do?

    A. Configure one connected network. Allow new VM networks created on this logical network to use network virtualization.
    B. Set the virtual LAN ID for the management network.
    C. Enable private virtual LAN (PVLAN) networks.
    D. Configure one connected network. Do NOT allow new VM networks created on this logical network to use network virtualization.

  • Question 74:

    You administer a Windows Server 2012 R2 server that has the Hyper-V role installed.

    You have the following virtual machines (VMs):

    You also have the following two switches:

    VM-Server1 has network connectivity to VM-Server2 and VM-Server3, as well as the host server, VM-Server4 has network connectivity to VM-Server5, but NOT to the host server. You need to configure VM-Server6 to ensure that VM-Server6 has network connectivity only to the other test VMs.

    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order

    Select and Place:

  • Question 75:

    A company plans to create a Hyper-V test environment that will contain three virtual machines (VMs). The VMs are projected to grow 1 GB in size each day. The VMs will be configured as follows:

    You must minimize the required amount of storage space by using the least amount of administrative effort.

    You need to recommend a storage solution.

    Which type of virtual disk type should you configure for each VM?

    A. differencing
    B. dynamically expanding
    C. fixed
    D. pass-through

  • Question 76:

    You administer two Windows 2012 R2 servers named SERVER1 and SERVER2. Both servers have the Hyper-V role installed. SERVER1 has network adapters that have Remote Direct Memory Access (RDMA) enabled. You plan to implement live migration in the environment.

    You have the following requirements:

    Use remote management tools to manage the live migration tasks.

    Optimize network performance during live migration.

    You need to configure live migration settings on each host server. In the Live Migrations section of the Hyper-V Settings window, which two options should you select? To answer, select the appropriate option buttons in the dialog box in the answer area.

    Hot Area:

  • Question 77:

    You are the virtualization administrator for an organization that manages private and public cloud resources. The organization has a Windows Azure subscription. You plan to move virtual machines to Windows Azure Infrastructure as a

    Service (IaaS) by using System Center 2012 R2 App Controller.

    You need to create a virtual machine template that allows virtual machines to be moved from Hyper-V to Windows Azure.

    What should you do?

    A. Create a new virtual machine that uses a .vhd file. Run the Sysprep tool on the virtual machine.
    B. Create a new Generation 2 virtual machine that uses a .vhdx file that is attached to a SCSI controller. Run the Sysprep tool on the virtual machine.
    C. Create a new virtual machine that uses a .vhdx file. Run the Sysprep tool on the virtual machine.
    D. Create a virtual machine by using a differencing disk. Use the Clone a virtual machine option to create new virtual machines.

  • Question 78:

    A company has Active Directory Domain Services (AD DS) domain controllers that run on Windows Server 2012 R2 servers. There are two forests, and each has a single domain. There is a two-way forest trust between the forests. The company uses Hyper-V for server virtualization. The Hyper-V environment contains the Hyper-V host servers as shown in the following table:

    You prepare to deploy System Center 2012 R2 Data Protection Manager (DPM) to back up the Hyper-V environment. The deployment must meet the following requirements: ensure that all Hyper-V servers can be backed up from a minimum of two DPM servers minimize the total number of DPM servers

    You need to deploy DPM to the environment. What should you deploy?

    A. four DPM servers in the internal network and two DPM servers in the perimeter network
    B. two DPM servers in the internal network and one DPM server in the perimeter network
    C. two DPM servers in the internal network only
    D. two DPM servers in the internal network and two DPM servers in the perimeter network

  • Question 79:

    You administer two Windows 2012 R2 servers that have the Hyper-V role installed. You plan to deploy a new Hyper-V cluster. The cluster instance must NOT be added to Active Directory. You need to deploy the cluster. What should you do?

    A. Run the Windows PowerShell cmdlet New-Cluster. Specify DNS for the AdministrativeAccessPoint parameter.
    B. Run the Windows PowerShell cmdlet New-Cluster. Specify Forest for the AdministrativeAccessPoint parameter.
    C. Run the Windows PowerShell cmdlet Get-Cluster. Specify DNS for the Domain parameter.
    D. Run the Windows PowerShell cmdlet New-Cluster. Specify ActiveDirectoryAndDNS for the AdministrativeAccessPoint parameter.

  • Question 80:

    You administer three Windows Server 2012 R2 servers named Server1, Server2, and Server3. The servers are configured as follows:

    Each virtual machine on Server1 has a 50-TB logical unit number (LUN) to store data. There is limited bandwidth between the local data center and Windows Azure. You have the following business continuity requirements:

    Virtual machines (VMs) on Server1 must be available within 30 minutes of an unexpected failure.

    VMs on Server1 must be available if the local datacenter is no longer available.

    You need to configure the environment.

    What should you do?

    A. Implement live migration from Server1 to Server2.
    B. Configure the VMs to use a checkpoint location on Server3. Then, create a daily snapshot.
    C. Enable Hyper-V replication between Server1 and Server2.
    D. Implement quick storage migration from Server1 to Server2.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-409 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.