You are using Microsoft Project.
Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.
You need to show one line item that displays all the requested information in the Gantt view.
What should you do?
A. Apply the Top Level Tasks filter.You are an independent project manager who uses Microsoft Project.
You work on multiple projects for different customers, and you use one project to manage all of their tasks. You invoice your customers on a monthly basis.
You use a custom field named Not Invoiced to identify all tasks that have not been invoiced, and you use a custom field named Customer Name to identify the customer.
You need to see all tasks that have not been invoiced, but only for one customer at a time.
What should you do?
A. Group by the Not Invoiced field and display the AutoFilter for the Customer name column.You are a project manager who uses Microsoft Project 2013. A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time. You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed. Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Your company uses Microsoft Project, and you are setting up an initial planning schedule.
You need to make sure that all new task durations are shown as estimated.
What should you do?
A. Enter the duration suffixed with -ed for estimated days.You are managing a project by using Microsoft Project, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column.
You need to resolve the issue.
What should you do?
A. Recalculate the project schedule.You are a project manager who uses Microsoft Project.
You have created a project which involves three other colleagues who are also using Microsoft Project. You and your colleagues are over budget and cannot spend any more money on this project.
To ensure that the latest version of the project file is always the one being used, you need to save, share, and sync this project plan File among your colleagues without using email.
What should you do?
A. Save and sync your project by using SkyDrive.You are using Microsoft Project.
You want the ability to see only tasks that have finish dates past their deadline date
You need to achieve this goal using a custom field.
What should you do?
A. Create a Lookup containing the values Yes and No against the Task Text1 custom field. Write a formula that compares the deadline date to the finish date and displays the correct value from the Lookup table.You are a project manager for an organization that uses Microsoft Project.
You manage a critical project across multiple regions. All information regarding the project must be shared through email directly to the stakeholders.
You have already added all of the tasks and milestones to Timeline, aiming to present the most important information of the project through graphs. You are not allowed to send the .mpp file to your stakeholders since they will not be able to
open it.
You need to share the Timeline view through email.
What should you do?
A. Select Visual Reports, select a Built-in template for Timeline views, and click Generate. When the report has been generated, copy and paste the output in the body of your email.You are managing a project schedule by using Microsoft Project.
You need to implement stoplight indicators that represent the difference between the baseline finish date and the planned finish date for a task.
Which three actions should you perform? Each correct answer presents part of the solution.
A. Assign graphic indicator values based on the values contained in the custom field.You are a senior project manager in a software development company. You manage your projects with Project Professional 2013. The development team is behind schedule due to a problem found in the architectural design of the database.
The lead architect estimates that redesigning the database will take approximately 30 hours.
You create a new manual task and assign it to the lead architect. However, the task has not been scheduled. You need to easily see a time phased view of all tasks for the lead architect in order to schedule the task for completion. Which
three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-343 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.