You manage a project for an organization that relies heavily on schedule baselines in Microsoft Project.
A change is approved for an in-progress project which you manage. You enter the new tasks necessary to include the changes to the project schedule.
You need to update the baseline in the most efficient manner.
What should you do?
A. Update the current baseline to the baseline1 fields.You are a senior project manager, and your organization uses Microsoft Project.
You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability.
You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.
What should you do?
A. Change the part-time resources' tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.You are a project manager who uses Microsoft Project.
You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.
The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.
You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.
What should you do?
A. Create a material resource with a material label of gallons. Enter $20 in the cost per use and $5.00 in the standard rate.Your organization uses Microsoft Project and Microsoft SharePoint.
You are responsible for a project with resources in different offices. All offices share the same SharePoint intranet, and all resources have valid accounts to log into the company intranet. Your project plan already has the correct names and
assignments for each resource involved in this project.
You need to share and receive project plan updates dynamically with your resources.
What should you do?
A. Sync with SharePoint Tasks List, automatically creating a Project Site synchronized to your Project Plan.Your company uses Microsoft Project.
An organization with project managers of varying expertise wants a simple, standard view that displays overall project status.
You need an out-of-box function that provides the ability to assess current, baseline, and actual work for the project.
Which view should you use?
A. Project Overview dashboardYou are entering tasks into a schedule by using Microsoft Project.
Some of the summary tasks contain an inaccurate duration for the task grouping, and the overall duration for the detail tasks is longer than the summary task indicates.
You need to ensure that the summary task duration accurately reflects the duration for the detail tasks in the grouping.
What should you do?
A. Remove task constraints in the summary grouping.You manage a project by using Microsoft Project.
The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8
hours for the day.
You need to solve this problem.
What should you add to the task?
A. A deadlineYou are a project manager who uses Microsoft Project.
You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.
What should you do?
A. For each new project, use the Status Bar to set new tasks to be auto scheduled.You are creating a schedule by using Microsoft Project. You enter the non-working days for the organization into the Standard calendar.
You need to save the updated calendar to use in future projects. What should you do?
A. Use Project Information to change the Project calendar.You are a project manager who uses Microsoft Project.
You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.
You need to assign the weekend working calendar to the task.
What should you do?
A. Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-343 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.